Preliminary analysis of Telecom's TSO model
Telecommunications Act: Preliminary analysis of
Telecom's TSO model and Commission's own proposed
model
The Commerce Commission today released the access network model that it proposes to use in estimating the annual cost to Telecom New Zealand Limited of complying with its telecommunications service obligations (TSO). The Commission's modelling forms part of its preparatory work for the publication of its draft and final TSO determination.
The Commission is using the Hybrid Cost Proxy Model (HCPM) model developed by the US Federal Communications Commission to calculate the key parts of the incremental cost of serving commercially non-viable customers.
In addition, the Commission released its preliminary analysis of Telecom's model for calculating the cost. Osmond Borthwick, Manager of the Commission's Network Access Group, said the Commission's preliminary view, to be tested through the consultative process, was that the Telecom model has a number of drawbacks and is of limited value to the Commission in calculating net TSO costs.
The Commission invites industry parties to make submissions on the HCPM model and the Commission's paper on the Telecom model, which will be the subject of an industry conference in Wellington from 15 to 16 May 2003.
The transport and switching network costs will be calculated by the Commission using a separate model developed by CostQuest Associates of the United States. This model will be released as soon as it is available. Comments may be made on the model at the May conference, and later written submissions will also be accepted.
Under the Telecommunications Act, the Commission is responsible for overseeing the TSO regime and apportioning the annual net cost between Telecom and other liable carriers. The Commission is currently working on setting the TSO cost for the period of 20 December 2001 (the date on which the Telecommunications Act was passed) to 30 June 2002 (the end of Telecom's financial year).
Current timeframe for TSO determination process: Date Activity 23 April Release of models the Commission will use to estimate the net TSO cost, together with supporting documentation Release of analysis of Telecom's TSO cost model 8 May Submissions due on material released 23 April 15, 16 May Conference in Wellington on Commission's modelling and inputs 30 May Release of TSO draft determination 30 June Submissions due on TSO draft determination 8, 9, 10 July Conference in Wellington on TSO draft determination
The TSO final determination will be released as soon as practicable after the completion of the conference on the draft determination.
The Commission's analysis of Telecom's model, plus documentation of the Commission's own proposed model will shortly be available on its website at: http://www.comcom.govt.nz/telecommunications/Obligations.cfm
Background Section 86 of the Telecommunications Act 2001 states: The Commission must make reasonable efforts to do the following things not later than 120 working days after the end of each financial year of a TSP under a TSO instrument: (a) prepare a draft determination of the matters set out in section 88: (b) give public notice of the draft determination: (c) include in the public notice the closing date for submissions, which must not be later than 20 working days after the date of giving public notice.
Section 90 of Telecommunications Act states: The Commission must make reasonable efforts to do the following things not later than 40 working days after the closing date for submissions under section 86(c): (a) prepare a final determination of the matters set out in section 92: (b) give public notice of the final determination: (c) give a copy of the determination to all liable persons in relation to the TSO instrument.
Media contact: Osmond Borthwick, Manager, Network Access Group Phone work (04) 924 3667
Gail Kernohan, Communications Adviser Phone work (04) 924 3709, mobile 029 924 3709
Commission media
releases can be viewed on its web site www.comcom.govt.nz
Under the Telecommunications Act
2001, the Commission is required to determine the net cost
to Telecom of complying with the Telecommunications Service
Obligations (TSO) Deed for Local Residential Telephone
Service. To assist with that determination, Telecom must,
not later than 60 days after the end of each financial year
(June 30), provide to the Commission calculations of the net
cost of complying with the TSO instrument during the
financial year. On 20 September 2002, Telecom provided the
Commission with its calculation of the net cost from 20
December 2001 to 30 June 2002, in accordance with s83 of the
Act. Telecom advised that the net cost of providing the
service required by the TSO Deed over that period was $226.5
million. The Commission wrote to Telecom on 14 August, 2
September and 25 October 2002, setting out requirements
relating to Telecom's calculation under s83 of the Act. On
8 November 2002, Telecom provided the results of Telecom's
TSO net cost calculation, incorporating the Commission's
requirements. The result was a TSO calculation of $112
million. On 4 April 2003, Telecom provided a fresh
calculation of the TSO net cost through rerunning its TSO
model with some improvements. Telecom noted that it had
identified and highlighted a number of minor errors in the
modelling. The revised annualised cost at 8.2% return on
capital was estimated at around $170 million. On 30
September 2002, the Commission released its Position Paper
on the TSO which stated that the Commission considered that
a bottom-up approach should be adopted for the modelling of
TSO costs. This was because it more directly estimated the
cost of an efficient service provider and was likely to be
better at identifying and estimating the unavoidable
incremental costs of providing services to groups of
customers within a service area. On 25 October 2002, the
Commission announced that it had decided to use the public
domain FCC Hybrid Cost Proxy Model (HCPM) as a bottom-up
model. However, the Commission also noted that the net cost
calculations produced by Telecom's model would provide
helpful input into the Commission's net cost calculation,
even though the model was not a bottom-up model as envisaged
by the Commission. The degree to which the Telecom model
will prove helpful depends on its consistency with the
provisions and purpose of the Act. Therefore, the
Commission has undertaken an assessment of whether the
Telecom calculation is consistent with the provisions and
purpose of the Act. To enable the assessment, the
Commission has sought, and Telecom has provided, information
on the Telecom model. The Commission has explored the
assumptions underlying the calculation, and the operation of
the cost model that produced the calculations. The
Commission has formed a preliminary view, to be tested
through the consultative process, that the Telecom model has
the following disadvantages, which limit its utility in
calculating net TSO costs: * the reliance on Telecom's
historic network configuration to estimate infrastructure
requirements; * placement of "modern equivalent assets"
[new, best-in-use technology] in the historic network
configuration to calculate capital costs; * the calculation
of an efficiency factor by benchmarking Telecom performance
against similar firms in the United States; * including the
cost of lines and infrastructure not serving current
customers in the capital cost modelled; * treating the cost
of serving business customers as incremental to the cost of
serving residential customers; * the calculation of core
switching costs on a fully allocated rather than incremental
basis; and * taking all residential customers as the
increment when calculating the cost of directory listings
and emergency calls. Given these features, the
Commission's preliminary view is that the initial results
are not suitable for use by the Commission in determining
the net TSO cost. The Commission is seeking feedback on
these preliminary views before the release of its Draft
Determination on the TSO. The Commission has also released
its model, based on HCPM, with the associated documentation,
for comment by the industry. The Commission is using the
HCPM model to calculate the key parts of the incremental
cost of serving commercially non-viable customers. The
HCPM model and the Commission's paper on the Telecom model
will be the subject of an industry conference from 15 to 16
May 2003. The transport and switching network costs will
be calculated using a model developed by CostQuest
Associates of the United States. This model will be
released as soon as it is available. Comments may be made
on the model at the May conference, and later written
submissions will also be accepted.