UPDATE @ 1:20 pm Tuesday 15 November
UPDATE @ 1:20 pm Tuesday 15 November
SUMMARY OF EVENTS:
- A 7.5 magnitude earthquake at 12:02 am on Monday 14 November 2016, caused significant damage to regions of the lower North Island and upper South Island of New Zealand.
- Vodafone’s network was impacted as a result of power cuts and damage to fibre. Teams worked through the day and night to assess and repair damage where possible. They have reinstated power to numerous sites and have planned a number of work arounds to get parts of Kaikoura connected to voice and text services.
- Coverage is restored in all areas except Waiau. Vodafone’s Instant Network (Femtocell over satellite) will be deployed to the Waiau area this afternoon, providing critical voice and text connectivity for many people in the area.
DAMAGED FIBRE CABLE - KAIKOURA:
- Please see here for a joint statement from Vodafone, Spark and Chorus regarding the status of the damaged fibre cable.
MOBILE NETWORK:
- Multiple cell sites were immediately impacted by power outages in a number of regions on the North and South Island.
o The areas of Kaikoura, Ward, Hundalee, Clarence and Waiau sustained significant damage and customers in these areas experienced a full loss of mobile services.
o By 6:30 pm last night, power had been restored to most sites, and where required back-up generators were transferred to sites and put into operation. This restored mobile voice, text and data services to all lower North Island sites and South Island sites that were affected by the power outages.
o Two sites in the South Island (Clarence and Waiau) are still down and our teams are working to restore services as quickly as possible:
Clarence – has some crossover coverage from the surrounding sites, and we are working to restore power on the site today.
Waiau - Vodafone will be establishing a temporary femtocell over satellite link early this afternoon to provide temporary coverage for people in Waiau.
FIXED BROADBAND - WELLINGTON:
- All but 1 FibreX/HFC node in the Wellington region has been reinstated. A very small group of customers remain impacted with a loss of service. We are working to restore services to these customers today.
- Some Vodafone home broadband customers may be eligible to take advantage of our ‘Always Connected’ promise. Where possible, we will load a free mobile data bundle onto customer’s mobile phone so they can remain connected via mobile hotspots.
Next update will be approx. 6pm this evening.
UPDATE @ 6 pm Monday 14 November
Customers in and around Kaikoura, Huandalee, Clarence, and Waiau are still experiencing degraded mobile services (a total of 3 sites are still down, a further 3 sites are partially down). This afternoon our technicians successfully installed a microwave backhaul link which has meant some people in these areas are now able to use voice and text services. Fixed line services in these areas and a number of other sites continue to be affected.
Vodafone’s is working closely with other telecommunications providers to repair damage to a significant fibre optic cable that runs through Kaikoura. The cable supports both fixed line and mobile networks. As the current conditions and the nature of the damage are very challenging, we are unable to give an expected restoration timeframe at this stage.
We encourage customers can check their fixed line service on the Chorus website - https://outages.chorus.co.nz/ We also encourage Vodafone home broadband customers to investigate whether they are eligible to take advantage of our ‘Always Connected’ promise. Where possible, we will load a free mobile data bundle onto customer’s mobile phone so they can remain connected via mobile hotspots.
A small number of FibreX/HFC customers in Wellington are also experiencing continued disruption to their service as 8 nodes are impacted by the power outage.
Our retail stores in Paraparaumu and Nelson have been assessed and cleared of any damage. These stores are now open to our staff and the public. However, our Lambton Quay building and retail stores in Queensgate and Cuba Street remain closed to staff and the public until further inspection has been carried out.
We will be able to advise on when we can resume normal business operations tomorrow morning.
Next update will be approx. 10am, Tuesday 15 November.
UPDATE @ 2:20 pm Monday 14 November 2016
Vodafone’s retail stores in
Paraparaumu and Nelson have been cleared of any damage.
These stores are now open to our staff and the
public.
Next update will be approx.
4:30pm
UPDATE @1:45 pm Monday 14 November 2016
Customers in and around Kaikoura, Huandalee, Clarence, and Waiau are still experiencing degraded mobile services (a total of 7 sites are affected).
Fixed line services in these areas and a number of other sites continue to be affected. Customers can check their fixed line service on the Chorus website - https://outages.chorus.co.nz/
A small number of FibreX/HFC customers in Wellington are also experiencing continued disruption to their service as 13 nodes are impacted by the power outage.
Our Wellington building at Lambton Quay has now been assessed and we are able to provide restricted access to Vodafone staff for essential and limited purposes only. We will be able to advise on when we can resume normal business operations a little later in the day following a further inspection.
Next update will be approx. 4:30pm
SPECIAL UPDATE @12:30 pm Monday 14 November 2016
To provide specific information for affected customers in and around Kaikoura - we have been informed that technicians as well as a back-up generator have been airlifted to the priority cell site in Kaikoura. Two other cell sites, have also been connected to back-up generators. We are in the process of restoring power and connectivity. No ETA can be provided at the moment, but we will keep you updated. Fixed line and broadband services are also affected and we are working hard to get these re-established as quickly as possible.
We are aware of a break in the fibre that serves this area and our technicians are working closely with Chorus. The break has been identified at the location of a major slip and work to repair it will commence as soon as it is safe to do so. Information for local residents can be found at https://outages.chorus.co.nz/
In order to provide important connectivity and access to emergency services for customers in this region, our technicians are looking to put in place a temporary coverage solution using femtocells, similar to what we provided to Fiji after Cyclone Winston.
Technicians continue to monitor all other sites.
#EQNZ for local information
UPDATE @9:30 am Monday 14 November 2016
Network technicians continue to monitor the mobile, fixed and broadband networks in earthquake affected regions. We can confirm that a small number of sites are affected by power outages and most have now kicked over to back-up battery or generator power. A small number of FibreX (HFC) customers in Wellington may be experiencing service interruptions. We are waiting for the power supply to settle before we send technicians to these sites.
We apologise for any service interruptions and urge people to refrain from making unnecessary calls, leaving the network free for emergency calls.
We are continuing to assess our retail stores and working closely with our teams to ensure the safety of customers and staff. Our stores in Lambton Quay, Cuba St, Queensgate, Porirua, Paraparaumu, Nelson and Blenheim currently remain closed. In Christchurch, our Riccarton stores are clear to open.
#EQNZ for local information.
UPDATE @7:30 am Monday 14 November 2016
Further to our updates across the morning, our technical teams have been working hard to ensure customers are able to remain connected. They have been able to assess the mobile and fixed networks and report that some sites in Wellington and Christchurch have been impacted by power cuts, there is no structural damage.
Back-up generators have arrived, or are on their way to key sites, should power outages continue across the day. We are sorry for any service disruption you may be experiencing. We know how important it is to stay connected with loved ones at times like this.
We are now assessing our retail stores and working closely with our teams to ensure the safety of customers and staff. We can advise that the following stores will remain closed until they have been checked and cleared for access: Lambton Quay, Cuba St, Queensgate, Porirua and Paraparaumu. The Christchurch retail stores are under review and we will update again shortly. #EQNZ for local information.
UPDATE @5:30 am Monday 14 November 2016
Following this morning’s severe earthquake 20km South East of Hanmer Springs, we have conducted a full assessment of the mobile and fixed line networks.
The power outages have impacted a number of our sites and initiated a switch over to back up generators to keep sites operational. There are a small number of sites down, mainly in the Wellington and Christchurch regions. In some cases customers in these regions are covered by crossover signal from nearby sites. Back-up generators are en-route to key sites. As power companies restore power, sites are coming back on, and we will keep you updated as we progress.
We hope everyone is safe and not too shaken. Stay strong, listen to civil defence reports and check on those around you. On social media use #EQNZ.
UPDATE @ 1.30 am Monday 14 November 2016
A severe earthquake struck the NZ South Island at 12:02am Monday and a tsunami warning has been issued for the eastern coast of the South Island.
We know that some of our mobile sites and fixed line cabinets have been impacted by power outages and we are working to identify the full extent of impact for our customers.
We hope everyone is ok. Please look out for each other and head to higher ground if you are on the eastern coast of the South Island.
We will update you as more information comes through.
UPDATE @ 6 pm Monday 14 November
Customers in and around
Kaikoura, Huandalee, Clarence, and Waiau are still
experiencing degraded mobile services (a total of 3 sites
are still down, a further 3 sites are partially down). This
afternoon our technicians successfully installed a microwave
backhaul link which has meant some people in these areas are
now able to use voice and text services. Fixed line services
in these areas and a number of other sites continue to be
affected.
Vodafone’s is working closely with other
telecommunications providers to repair damage to a
significant fibre optic cable that runs through Kaikoura.
The cable supports both fixed line and mobile networks. As
the current conditions and the nature of the damage are very
challenging, we are unable to give an expected restoration
timeframe at this stage.
We encourage customers can
check their fixed line service on the Chorus website - https://outages.chorus.co.nz/ We also
encourage Vodafone home broadband customers to investigate
whether they are eligible to take advantage of our ‘Always Connected’ promise. Where
possible, we will load a free mobile data bundle onto
customer’s mobile phone so they can remain connected via
mobile hotspots.
A small number of FibreX/HFC customers
in Wellington are also experiencing continued disruption to
their service as 8 nodes are impacted by the power outage.
Our retail stores in Paraparaumu and Nelson have been
assessed and cleared of any damage. These stores are now
open to our staff and the public. However, our Lambton Quay
building and retail stores in Queensgate and Cuba Street
remain closed to staff and the public until further
inspection has been carried out.
We will be able to
advise on when we can resume normal business operations
tomorrow morning.
Next update will be approx. 10am,
Tuesday 15 November.
UPDATE @ 2:20 pm Monday 14 November 2016
Vodafone’s retail stores in
Paraparaumu and Nelson have been cleared of any damage.
These stores are now open to our staff and the
public.
Next update will be approx.
4:30pm
UPDATE @1:45 pm Monday 14 November 2016
Customers in and around Kaikoura, Huandalee, Clarence, and Waiau are still experiencing degraded mobile services (a total of 7 sites are affected).
Fixed line services in these areas and a number of other sites continue to be affected. Customers can check their fixed line service on the Chorus website - https://outages.chorus.co.nz/
A small number of FibreX/HFC customers in Wellington are also experiencing continued disruption to their service as 13 nodes are impacted by the power outage.
Our Wellington building at Lambton Quay has now been assessed and we are able to provide restricted access to Vodafone staff for essential and limited purposes only. We will be able to advise on when we can resume normal business operations a little later in the day following a further inspection.
Next update will be approx. 4:30pm
SPECIAL UPDATE @12:30 pm Monday 14 November 2016
To provide specific information for affected customers in and around Kaikoura - we have been informed that technicians as well as a back-up generator have been airlifted to the priority cell site in Kaikoura. Two other cell sites, have also been connected to back-up generators. We are in the process of restoring power and connectivity. No ETA can be provided at the moment, but we will keep you updated. Fixed line and broadband services are also affected and we are working hard to get these re-established as quickly as possible.
We are aware of a break in the fibre that serves this area and our technicians are working closely with Chorus. The break has been identified at the location of a major slip and work to repair it will commence as soon as it is safe to do so. Information for local residents can be found at https://outages.chorus.co.nz/
In order to provide important connectivity and access to emergency services for customers in this region, our technicians are looking to put in place a temporary coverage solution using femtocells, similar to what we provided to Fiji after Cyclone Winston.
Technicians continue to monitor all other sites.
#EQNZ for local information
UPDATE @9:30 am Monday 14 November 2016
Network technicians continue to monitor the mobile, fixed and broadband networks in earthquake affected regions. We can confirm that a small number of sites are affected by power outages and most have now kicked over to back-up battery or generator power. A small number of FibreX (HFC) customers in Wellington may be experiencing service interruptions. We are waiting for the power supply to settle before we send technicians to these sites.
We apologise for any service interruptions and urge people to refrain from making unnecessary calls, leaving the network free for emergency calls.
We are continuing to assess our retail stores and working closely with our teams to ensure the safety of customers and staff. Our stores in Lambton Quay, Cuba St, Queensgate, Porirua, Paraparaumu, Nelson and Blenheim currently remain closed. In Christchurch, our Riccarton stores are clear to open.
#EQNZ for local information
UPDATE @7:30 am Monday 14 November 2016
Further to our updates across the morning, our technical teams have been working hard to ensure customers are able to remain connected. They have been able to assess the mobile and fixed networks and report that some sites in Wellington and Christchurch have been impacted by power cuts, there is no structural damage.
Back-up generators have arrived, or are on their way to key sites, should power outages continue across the day. We are sorry for any service disruption you may be experiencing. We know how important it is to stay connected with loved ones at times like this.
We are now assessing our retail stores and working closely with our teams to ensure the safety of customers and staff. We can advise that the following stores will remain closed until they have been checked and cleared for access: Lambton Quay, Cuba St, Queensgate, Porirua and Paraparaumu. The Christchurch retail stores are under review and we will update again shortly. #EQNZ for local information
UPDATE @5:30 am Monday 14 November 2016
Following this morning’s severe earthquake 20km South East of Hanmer Springs, we have conducted a full assessment of the mobile and fixed line networks.
The power outages have impacted a number of our sites and initiated a switch over to back up generators to keep sites operational. There are a small number of sites down, mainly in the Wellington and Christchurch regions. In some cases customers in these regions are covered by crossover signal from nearby sites. Back-up generators are en-route to key sites. As power companies restore power, sites are coming back on, and we will keep you updated as we progress.
We hope everyone is safe and not too shaken. Stay strong, listen to civil defence reports and check on those around you. On social media use #EQNZ.
UPDATE @ 1.30 am Monday 14 November 2016
A severe earthquake struck the NZ South Island at 12:02am Monday and a tsunami warning has been issued for the eastern coast of the South Island.
We know that some of our mobile sites and fixed line cabinets have been impacted by power outages and we are working to identify the full extent of impact for our customers.
We hope everyone is ok. Please look out for each other and head to higher ground if you are on the eastern coast of the South Island.
We will update you as more information comes through.