CMJ traffic bulletin: 10 June until 15 June
Auckland Regional Office
9 June 2006
CMJ traffic bulletin: Saturday 10 June until Thursday 15 June
Transit New Zealand would like to advise motorists of proposed closures for work on the Central Motorway Junction upgrade over the next week.
CMJ Stage 2 Full motorway closures: Sunday 11 until Thursday 15 June – CLOSED – overnight from 9.30pm until 5am the following morning:
- Southern Motorway (SH1) southbound between Cook St off-ramp and Hobson St on-ramp
- Southern Motorway (SH1) northbound between Symonds/Port/Wellesley St off-ramp and Wellington St on-ramp
Ramp and link closures: Sunday 11 until Thursday 15 June – CLOSED – overnight from 9pm until 5am the following morning:
- Northwestern Motorway (SH16) to Nelson St off-ramp citybound
Sunday 11 and Monday 12 June – CLOSED – overnight from 11pm until 5am the following morning:
- Hobson St on-ramp to Northwestern Motorway (SH16) westbound
Tuesday 13 until Thursday 15 June – CLOSED – overnight from 9pm until 5am the following morning:
- Newton Rd on-ramp to Northwestern Motorway (SH16) westbound
Tuesday 13 until Thursday 15 June – CLOSED – overnight from 11pm until 5am the following morning:
- Northwestern Motorway (SH16) to St Lukes Rd off-ramp westbound
During these times motorists are requested to follow the signposted detours while the closures are in operation.
Transit New Zealand regrets any inconvenience caused.
In the event of inclement weather, the closures will be postponed to the next fine evening.
The CMJ Project Stage 1 of Transit’s Central Motorway Junction upgrade project, completed in January 2005, covers the section of motorway between the Upper Queen St over-bridge and Gillies Ave on- and off-ramps.
Phone 0800 ToFreeflow (0800 863 733).
Stage 2 of Transit’s Central Motorway Junction upgrade project extends from Bond St on the Northwestern Motorway (SH16) to the interface with CMJ Stage 1 near Symonds St and from Cook St on the Southern Motorway (SH1) to Symonds St. The SH16 Newton Rd to Western Springs Auxiliary Lane westbound widening project is included in CMJ Stage 2 works.
Project information centre: 13-19 Howe St, Freeman’s Bay, Monday to Thursday 9.00am – 4.30pm, Friday 9.00am – 4.00pm, and Saturday by prior booking only.
Phone 0800 CMJ Core (0800 265 2673).
Transit New Zealand Regional Manager (acting) Peter Spies tel. (09) 368 2000. Visit www.transit.govt.nz for more information._