Strengthening Auckland's Regional Governance
Strengthening Auckland's Regional Governance
Preliminary Auckland Regional Council
Response
15 November 2006
Table of
Contents
1. Introduction 3
2. Purpose 3
3. Background 3
4. Analysis 4
4.1 The
case for change 4
4.2 Options for regional
governance 8
4.3 Principle-based
assessment 8
4.4 Initial response to the
models 9
4.5 Summary 12
5. Preliminary arc
response 12
5.1 Key elements 13
5.2 An enhanced
regional council 14
5.3 Transition and transfer of
functions and responsibilities 16
5.4 Regional
Sustainable Development Forum 17
5.5 Transport – RLTS
and ARTA 18
5.6 Water 19
5.7 Economic
development 19
5.8 Potential regional role in urban
renewal 20
5.9 Regional
amenities 21
5.10 Representation 21
5.11 Establishment 21
5.12 Other
matters 21
6. Public consultation 22
STRENGTHENING
AUCKLAND'S REGIONAL GOVERNANCE - PRELIMINARY ARC
RESPONSE
Report from the Auckland Regional Council: 15
November 2006
1. INTRODUCTION
This report outlines the
ARC’s preliminary response to the Strengthening Auckland
Regional Governance project. The discussion paper from the
Joint Officials Group (JOG) was issued on Friday 3 November.
Council considered the discussion paper and an accompanying
officer report at an extra-ordinary meeting of the Council
held on Wednesday 8 November.
This report follows
Council consideration of the Options and Issues paper and
reflects resolutions passed by Council at the meeting.
The report provides:
• Background to the
project;
• Initial response to the three governance
models outlined in the JOG discussion paper;
• A
preliminary ARC response.
2. PURPOSE
The purpose of
this paper is to outline a preliminary ARC response to the
Options and Issues paper (Strengthening Auckland’s
Regional Governance – Issues and Options, discussion paper
for the councils of the Auckland region, 3 November 2006).
3. BACKGROUND
A variety of events have created a
stronger impetus from various constituencies for local
government reform in Auckland. The eight councils in the
Auckland region have resolved to participate in the project,
to strengthen regional governance. The project will deliver
proposals for central government consideration in December
2006, to enable any necessary legislation to be drafted,
consulted on and passed prior to the October 2007 local body
elections.
The ARC is providing feedback on the
discussion paper first, through this report, and will then
be asked to resolve a position on a final set of proposals
(by the end of November).
The Council has endorsed the
ARC presentation to the Mayoral Forum on 15 September and
this forms the initial basis for the response. Weekly
meetings with ARC Councillors have occurred and input has
been received through these meetings to assist in the
development of this preliminary response. In addition, a
regional forum led by the ARC involving all elected
representatives of the region, mayors, councillors and
community board members, was convened on 2 October and 6
November to discuss regional governance
reform.
4. ANALYSIS
4.1 The case for change
The
broad case for change is outlined in the discussion paper
(Strengthening Auckland’s Regional Governance – Issues
and Options – Discussion Paper for the Councils of the
Auckland Region – 3 November 2006). There are some
emerging themes that suggest local governance arrangements
could be improved to:
• Provide better value for money
for Aucklanders through improving service standards,
efficiencies, greater consistency and reducing
costs;
• Produce a coherent vision for the future,
leadership and a unified approach for discussions with
central government on social, economic, environmental and
cultural regional issues;
• Support decision-making
about interrelated issues in a more integrated way, more
quickly and without relitigation;
• Better integration
with Central Government achieving more certainty about
funding and delivery;
• Better facilitate local
democracy and helping to address emerging local social
problems.
From an ARC perspective there are a number of
compelling reasons that suggest changes will be necessary to
meet the regional challenges facing Auckland, both today and
into the future. New ways of thinking and ‘new ways of
doing’ will be required.
4.1.1 One city-region – many
communities
Despite the political boundaries,
functionally Auckland is one city/region. Auckland works as
one regional economy, one labour market, and despite
multiple providers, Auckland has one transport system.
Water networks cross local authority boundaries, and
catchments in one part of the region have an impact on
receiving environments in another.
This is not to
ignore the importance of unique local communities and
places. These are essential for the health and
distinctiveness of the whole region. There are many issues
that are best dealt with at the local level.
However, the
ongoing growth, size and complexity of the Auckland region
create a number of distinct opportunities. As New
Zealand’s largest metropolitan urban region Auckland also
has specific challenges. Auckland’s growth has major
impacts on the region’s rural communities and settlements
as well as the neighbouring regions of Northland, Waikato,
and Bay of Plenty. The pace and cost of growth coupled with
the historic underinvestment in key infrastructure means
Auckland cannot afford to make poor decisions that result in
a further misallocation of resources. There is a need to
deal with problems that are essentially regional in nature
at the appropriate scale.
4.1.2 Clarifying
functions and responsibilities
The enactment of the Local
Government Act (LGA) 2002 provided the opportunity for local
government to reassess, through a process of identifying
community outcomes, what and how it undertakes activities.
The intention was to provide a more explicit rationale and a
clearer linkage between activities and local authority goals
and community priorities. However, in practice there has
been a blurring of lines of responsibility between regional
and local government with the result that the ‘division of
labour’ between regional and local levels has become more
ambiguous and less well defined. The strengthening regional
governance process provides an opportunity to address the
current ambiguity and provide a much clearer definition of
responsibilities (i.e. the division of labour) between the
regional and local spheres of governance.
It is also
important to recognise that questions of strengthening
regional governance do not simply involve the regional
council and territorial authorities (TAs). Regional and
local governance (including community boards) also involves
citizens, non-governmental organisations, businesses, and
other civil sector stakeholders who have an important role
to play. Central government has an essential role and
enhancing the relationship between regional and central
government is critical to achieving successful public
service outcomes. Providing a stronger voice for the region
and creating a more effective partnership with central
government and other sectors provides a far greater ability
for the region to obtain the support that is needed. A
stronger regional voice provides the prospect that the real
issues affecting the region can be more successfully
advocated and addressed.
4.1.3 Implementing the Regional
Growth Strategy
It is increasingly recognised that there
has also been a failure to fully achieve the outcomes
intended in the Regional Growth Strategy (RGS). Since the
adoption of the Growth Strategy, the majority of dwelling
growth continues to occur in greenfield areas and as urban
infill. Intensification has been slow to occur in the areas
identified for growth. Developers indicate that there is
little incentive for intensification of town centres and
corridors and that they are looking for higher levels of
leadership to encourage this. Fragmented land ownership has
limited the ability of the market to deliver comprehensive
re-development and effectively mitigate impacts on
neighbours. Progress towards implementing sector agreements
has been slower than programmed. It is evident that
implementation of the Regional Growth Strategy has been
under-resourced and efforts to align councils spending
(through LTCCPs and asset management) with the Growth
Strategy have been weak. Generally there has been
insufficient investment in growth nodes, both in terms of
infrastructure and planning.
While there are some good
examples of urban development, poor built environment
outcomes (e.g. aesthetically unattractive and poorly
designed buildings), and development that is poorly
integrated with the surrounding neighbourhood and transport,
continue. Infrastructure provision is not leading or
supporting appropriate development. Developers find council
processes and requirements difficult to negotiate,
inconsistent and uncertain. Short-term, local pressures
undermine a regional long-term view and commitment to RGS
implementation.
Lessons from city-regions in other
parts of the world suggest that the intent of the RGS will
not be implemented by zoning and regulation on their own.
New approaches are being investigated in the review of the
RGS (underway) and include:
• Prioritising growth
centres in which significant investment, planning and other
initiatives are focused;
• More active involvement in
property;
• Direct investment in infrastructure;
• Establishing lead implementation agencies tasked
with managing redevelopment including planning, land
amalgamation, infrastructure provision and recovering
costs.
4.1.4 Implementing the Regional Land Transport
Strategy
Transport service delivery remains fragmented
and under funded and a range of Auckland only provisions
apply, for example the Auckland Regional Land Transport
Strategy cannot include specific projects. Currently only
ARTA is required to give effect to the Auckland Regional
Land Transport Strategy. The obligations on both Transit
New Zealand and the other Auckland local authorities are
much weaker. At present, the ARC is unable to fully fund
the implementation of the strategy. The result is that
despite enjoying a very high level of support the Regional
Land Transport Strategy will not be implemented in the
current system of governance and funding. Ensuring the
ability to both fund and implement the RLTS is a critical
success factor.
4.1.5 Councillors’
responsibilities
The obligations of councils and
councillors are first and foremost to act in the public
interest to their local community. Section 12(4) of the
LGA2002 requires that “A territorial authority must
exercise its powers under this section wholly or principally
for the benefit of its district”, with a similar provision
in s.12(5) for Regional Councils. The ‘councillors oath
of office’ (Schedule 7, Part 1, Section 14 LGA2002) echoes
that obligation as follows:
“I, AB, declare that I will
faithfully and impartially, and according to the best of my
skill and judgement, execute and perform, in the best
interests of [region or district], the powers, authorities,
and duties vested in, or imposed upon, me as [mayor or
chairperson or member] of the [local authority] by virtue of
the Local Government Act 2002, the Local Government Official
Information and Meetings Act 1987, or any other
Act.”
Despite the goodwill of councillors these
obligations effectively mean that city and district councils
find decisions that may be in the best interests of the
region as a whole, but possibly disadvantage their district,
extremely difficult. This elementary conflict of obligation
makes it difficult to achieve a comprehensive unified vision
and plan. It places limits on the extent to which
collaborative mechanisms can work in the interests of the
region as a whole.
4.1.6 Objectives of the Metro
Project Action Plan
The Metro Action Plan suggests that
fragmented planning, decision-making and implementation are
a major impediment to Auckland’s success. The
implementation of several of the Metro Action Plan
objectives and actions requires local government to reflect
on and change the way in which it operates. There are a
number of ways in which the objectives of the Metro Action
Plan could be met, but some options for strengthening
regional governance are more likely than others to support
the objectives.
4.1.7 Reducing regional
inefficiencies
The way certain regional activities are
currently provided and funded highlight some of the
inefficiencies that exist under current arrangements.
Achieving the consensus and support of seven TAs (or all
eight Councils) through a confederate approach has proven
difficult, especially when it requires each Council to spend
money. Examples of this difficulty are: the lengthy debate
over the funding of the joint Civil Defence and Emergency
Management responsibilities and the current debate over the
funding of regional facilities. Apart from the very costly
process of considering funding models, the net result is
that a disproportionate share of responsibility often lies
with certain Councils.
4.1.8 Improved funding
mechanisms
The public have clearly signalled basic
concerns over the magnitude and frequency of rates
increases. While there is a substantial gap between the
ARCs ability to fund public transport and levels of
investment that are required to give effect to the RLTS
there are also major financial pressures on the territorial
authorities. The Strengthening Auckland’s Regional
Governance project must deliver new and improved funding
mechanisms and also focus on the need to achieve
efficiencies if the current regional strategies are to be
effectively implemented.
4.1.9 Central government’s
role
In many areas where it has not been possible to
effectively implement regional strategies a major factor has
been the inability, or unwillingness, of central government
to deliver key parts of the strategy or change either what
they deliver, or the way in which they deliver it. Examples
of this problem are: the current misalignment with respect
to the Regional Land Transport Strategy and the Rail
Development Plan including electrification of the rail
network, and the failure to progress reform of the Transport
Services Licensing Act. Strengthening Regional Governance
may well require the Government to change the way that it
acts and possibly the way in which it delivers and funds
some activities.
4.1.10 Shared services
There are few
legal impediments to the provision of shared services within
the local government sector. Over many years a number of
opportunities to realise savings and efficiencies through
the provision of shared services, for instance rates
billing, have been identified. Few of these have been
attempted. Notable successes are the recent shared back
room systems and services supporting libraries across the
region, and the joint traffic management unit that has
combined operational traffic management across all TAs and
Transit New Zealand. There are weak incentives to realise
the potential efficiencies through developing shared
services.
4.1.11 National consistency
While there is a
case to say that the scale and nature of the challenges of
dealing with the sustainable development of Auckland may
require unique approaches, there is also a strong case for
national consistency. As a matter of principle it would
seem that any departure from the national model of local
government would need to be well considered and supported by
a very strong case for an Auckland specific
solution.
4.2 Options for regional governance
The JOG
paper identifies 3 broad options for reform each reflecting
different philosophies.
Further details are provided in
the discussion paper.
The key features of Option 1
are:
• It essentially builds on the existing modes of
operations;
• The independent sovereignty of each of
the existing Councils remains, but this option relies on a
much stronger commitment to work together;
• Participation would be voluntary.
The key
features of Option 2 are:
• The agreement to create a
regional assembly comprising representatives of the local
authorities;
• A ceding of power (relative to the
status quo) to the regional assembly;
• The binding of
all local authorities to give effect to strategies adopted
by the regional assembly.
The key features of Option 3
are:
• An enhanced regional body to plan, deliver and
fund regional strategies;
• Reduced functions and
decision-making (relative to the status quo) for territorial
authorities and potentially central government.
Further
details are provided in the discussion
paper.
4.3 Principle-based assessment
The ARC has
previously endorsed a principle-based approach to the
assessment of governance models. A good governance model for
Auckland should:
• Give effect to the purpose of local
government to enable democratic local decision-making and
action by, and on behalf of, communities; and promote the
social, economic, environmental, and cultural well-being of
communities in the present and for the future;
• Better enable the achievement of a unified vision
and plan for the Auckland region to increase its
international competitiveness and long term
sustainability;
• Ensure that decisions are taken at
the level of governance closest to those affected, best
informed and best placed to deal with consequences, and
coordinated between the different spheres of
government;
• Provide for clear accountability to the
public for outcomes, use of public funds and stewardship of
public assets – no taxation without
representation;
• Be cost efficient and
effective;
• Deliver equitable impacts across the
region;
• Be resilient into the future, and be able to
deal with increasing uncertainty, complexity, diversity and
change.
An important principle is the need to ensure that
the proposal provides benefits that outweigh the costs of
the reform and leads to more cost-effective services. In
the time that has been available staff have not been able to
undertake an analysis to quantify the likely benefits and
costs of the options.
It is important to consider initial
transition costs and longer term gains. This includes
consideration of:
• The benefits of streamlined
decision-making, including the ability to reach a final
decision in a shorter period of time;
• The benefits of
enhanced delivery, including the ability to take action and
implement decisions in a shorter period of time;
• The
likelihood of efficiencies and savings as a result of less
duplication and less fragmentation;
• The benefits of
more effective interface with central government and other
sectors, and decision-making on regional issues that
reflects the regional community of interest, and ensures
better alignment of expenditure and effort.
4.4 Initial
response to the models
4.4.1 Option 1 – voluntary
cooperative decision-making and
delivery
Advantages
The advantages of this model are
that it builds collaboration and partnership efforts around
the development of a common vision. It continues current
democratic local decision-making.
The preparation of
“One Plan” for Auckland by the Regional Development
Forum, would provide overarching direction for the region
and priority infrastructure investments, regional facilities
and other actions required to deliver on economic,
environmental, social and cultural outcomes from a regional
perspective. This would provide the basis for a more
unified vision.
The transition costs involved in Option 1
could be modest as it involves minimal change to the status
quo. The key changes achievable in Option 1 could be the
creation of new regional entities with responsibility for
the vertical integration of service delivery for transport,
water, economic development etc. Provided that the
governance framework for these entities was strong this
approach could deliver significant benefits through enhanced
efficiency and more aligned
decision-making.
Disadvantages
The difficulty with
Option 1 is that it provides little that is different to the
status quo. It therefore fails to provide a compelling
solution to the problems identified above. This option does
not really present a new division of labour between what is
regional and what is local. It therefore fails to ensure
that decisions are made at the level of governance closest
to those affected and best able to deal with the
consequences.
In addition to failing to solve the key
problems of the status quo, Option 1 also contains an
expanded confederate model for ownership and governance of
regional entities. This would potentially extend the
relatively weak governance structure that has applied to
ARTNL and Watercare to ARTA, an expanded water authority, a
regional economic development agency and an urban renewal
agency. The inherent weakness in the proposed ownership
model means that these new entities are unlikely to deliver
the desired savings or efficiencies. Joint or club
ownership may also reduce accountability to the public for
outcomes, the use of public funds and the stewardship of
public assets.
Because Option 1 does not adequately
address the problems that are the drivers for the
Strengthening Regional Governance work it is unlikely to be
resilient into the future. Adopting Option 1 now is likely
to lead to calls for further reform in the
future.
4.4.2 Option 2 – shared binding
decision-making
Advantages
This option addresses some
of the current shortcomings by creating the potential for
greater support for regional strategies. There is also a
greater likelihood of implementation through the ability of
the new regional assembly to ensure compliance with regional
strategies. Accordingly, this option is more likely to
deliver a unified vision and plan for the region than Option
1.
Option 2 has a ‘give effect to’ clause which
addresses many of the short-comings of the current
arrangements and provides a mechanism to overcome
fragmentation, poor implementation and funding issues. The
mechanism provides a greater likelihood of compliance and
collective action in the regional interest.
This option
continues much of the current framework for local democratic
decision-making, however, the balance of decision-making
responsibility between what is regional, what is local, and
what is done jointly by the regional assembly is not
clear.
Disadvantages
It is considered that the model
outlined in Option 2 creates a very significant governance
and accountability problem and would in fact make clear
accountability to the public for outcomes, the use of public
funds and the stewardship of public assets worse than the
status quo. This is because the elected representatives who
are members of the regional assembly will make decisions
that are then imposed on councils other than their own.
This has significant implications for democratic
decision-making. The model is significantly at odds with
the framework of the LGA 2002 and the consultation and
decision-making obligations of Councils. It could
significantly alter the way in which councils set rates and
constrain their ability to initiate actions. For example,
the regional assembly could require councils to initiate
changes to their regulatory frameworks, or require councils
to make funding commitments to support a regional strategy.
Councils would be left with the prospect of levying their
ratepayers for actions and decisions made by the regional
assembly. Accountability to the public under such a
scenario becomes extremely compromised.
In practice,
Option 2 would create on-going conflicts between the
regional assembly and the parent institutions (i.e.
TAs/regional authority), or deliver decisions that are based
around the lowest common denominator agreements. Reaching
agreement, or even binding majority decisions within the
regional assembly could be very time consuming.
In
addition it is unclear how regional priorities would be
determined and how the regionally mandated body would
influence those priorities. The JOG has not considered how
the regional assembly would make decisions. Options
include; equal representation for all eight councils, or
some form of weighted representation, or weighted voting.
The nature of the weighting and proportionality involved
would be highly contentious. For example weighting could
lead to the larger TAs being able to hold the balance of
power at the expense of the smaller councils.
Alternatively, equal representation could result in smaller
communities exercising disproportionate influence to secure
their own interests. Either way, the prospects of good
decision-making that can address issues in the best
interests of the whole region are less favourable than
Option 3.
On balance Option 2 has the potential to
deliver better decision-making and implementation than
either the status quo, or Option 1. However in practice the
way in which the Regional Assembly is structured means that
there is likely to be a greater chance that the costs of
transition and costs inherent in the problematic model of
decision-making, exceed the benefits.
4.4.3 Option 3
– multifunctional regional authority (integrating strategy
and delivery)
Advantages
It is considered that Option
3 has a number of advantages over both the status quo and
the two other options. Option 3 creates a better defined
division of labour and responsibilities (with the consequent
decision-making, accountability and funding) between
regional and local authorities. This option also preserves
democratic local decision-making, although in a different
form from the status quo.
Similarly, by ensuring that
regional issues/functions are allocated to the
democratically elected (and thereby mandated) regional body
and that other issues are dealt with locally it ensures that
all communities affected by those regional issues have a say
in those issues.
Under this option, creating a unified
vision for the region is made easier as overlaps between the
regional and local authorities are minimised.
This is the
option that also has the greatest prospect of addressing the
short-comings of the current system through the alignment of
tools for delivery of regional functions (planning, funding,
ownership) in one regional organisation. It provides for
better, faster decision-making and ensures that the
financial consequences are considered as part of the
decision. As a result, this option would make it easier to
implement strategies.
Of all the models, Option 3 is most
likely to be resilient in the future as it is considered to
best address the underlying problems of existing
institutional fragmentation and duplication, as well as
provide for clear lines of public accountability for
regional decision-making.
Option 3 has the greatest
transition costs, but it also has the greatest scope for
securing savings and other benefits. It also offers the
potential for faster decision-making and implementation than
the other two options. It also offers greater likelihood of
realising efficiencies because of the way it combines
financial responsibility with public accountability for
outcomes, the use of public funds and the stewardship of
public assets.
Disadvantages
The main disadvantage
of this model is that it has the greatest transition costs
including risks associated with its implementation. It also
has the greatest impact on some of the TAs and their current
operations as a shift in function to a regional body will
need to be accompanied by a corresponding reduction in
function at a TA level.
This option relies on the
integration of strategy, funding and delivery within one
regional authority. However, there would still be a major
need for collaborative mechanisms to achieve the outcomes
sought in regional strategies. The achievement of many
aspects to regional strategies depends upon the action of
Government, major private sector infrastructure providers,
and the actions of individuals, groups and companies.
Effective engagement with these groups would be an important
success factor for the new regional
authority.
4.5 Summary
On balance Option 3 provides
the most attractive solution to the shortcomings of the
current framework. It also stands up well across the
principles that the ARC has endorsed for the assessment of
governance models. However, there are some significant
aspects of Option 3 that warrant further refinement or
change. These are:
• The significant transition costs
and risks associated with moving to Option 3 and ways in
which the transition can be managed so that it does not
de-stabilise decision-making and investment;
• Ensuring
that the functions and responsibilities that are transferred
result in efficiencies, cost savings and more robust and
more timely decisions;
• Re-organising the structure of
local government without providing additional funding
mechanisms will not deliver the level of investment required
to successfully implement regional
strategies;
• Addressing the on-going role and
responsibilities of community boards; and
• Ensuring
that mechanisms for effective collaboration are preserved
and enhanced where they are required.
5. PRELIMINARY ARC
RESPONSE
The analysis of options presented above shows
that whilst option 3 is the best of the three options
presented in the Issues and Options paper there are still
some significant aspects of Option 3 that require further
refinement or change. It is therefore appropriate for the
ARC to go beyond an assessment of the three options
contained in the Issues and Options paper and consider an
alternative response that the Council considers better
achieves the objectives of reform.
This preliminary
response presents an evolution of the Local Government
(Auckland) Amendment Act 2002 (LGAAA) reforms with many of
the features of Option 3. It also provides for an important
new regional forum that is derived from Option 1 of the JOG
paper. In addition, it brings together a number of related
reforms that the Council has sought for some time, in
particular transport reforms that are required to achieve
greater value for money in the deliver of public transport
services.
The proposed ARC response is therefore more in
the nature of a package of reforms designed to enhance
regional government than just a response to the structural
options dealt with by the Issues and Options
paper.
5.1 Key elements
The key elements of the
proposed ARC response are:
• A strengthened regional
council that continues a strong collaborative approach with
the regional integration of strategy, funding and delivery
for transport, water and economic development. There is also
the potential for a regional role in urban
renewal;
• The development of a new Regional
Sustainable Development Forum to provide the inclusive
collaborative environment with city and district councils to
develop one plan for the sustainable development of the
region, integrating strategies and actions across all
aspects of the well-being of the region. The role of the
regional council’s delivery agencies is to give effect to
the sustainable development plan;
• The need for
stronger national level policy guidance together with
greater levels of national funding for Auckland’s regional
infrastructure. In particular the need to develop national
policies, including a National Policy Statement on
population, growth and development for New Zealand;
• A
staged transition process that establishes the strengthened
regional authority with appropriate regional functions, and
at a later stage the transfer of appropriate functions from
other agencies, if this is considered desirable and mutually
agreed;
• Retaining the present system of democratic
representation across the local government sector including
community boards, local councils (TAs) and the regional
council;
• The provision of new funding mechanisms (a
regional fuel tax and regional development contributions) to
support the strengthened regional council and ensure that it
has the financial capability to match its
responsibilities;
• Targeted shared services across all
of the local authorities in the region (shared rates
billing), and stronger incentives to achieve cost-savings
and efficiencies through shared services in other
areas;
• A regional forum open to all elected
representatives of the region, Mayors, Councillors and
Community board members to meet periodically to discuss
matters of regional significance (note the ARC has already
convened two of these to discuss regional governance);
• The inclusion of the whole of Franklin District
Council in the Auckland region;
• The civil defence
emergency management service as a responsibility of the
regional council;
• The funding of agreed regional
amenities and services such as, regional surf life saving,
Auckland Philharmonia, etc.
• The tidy up of a small
number of legislative anomalies and inconsistencies in a
range of Auckland specific legislation, including the Local
Government Act 1974, LGA 2002 and the LGAAA
2004;
• Some broader transport reforms, including
completing of the reform of the Transport Services Licensing
Act and the related review of Land Transport New Zealand’s
procurement procedures relating to passenger
transport.
5.2 An enhanced regional council
The broad
structure of the proposed strengthened regional council is
shown in
Figure 1. The enhanced regional council would
continue to deliver all of the current responsibilities and
functions of the ARC including regional parks, environmental
and coastal protection and management, regional policies and
regional plans. In addition it could progressively take on,
subject to further analysis, integrated strategy, funding
and delivery responsibilities for transport, water, economic
development and potentially urban renewal.
Each of
these responsibilities is further discussed overleaf.
The
proposed ARC approach targets integration of strategy,
funding and implementation in those areas which:
• Are
best understood;
• Have the potential through
integration to significantly enhance the delivery of
services, better align investment decisions and deliver
considerable efficiencies and savings through combined
operation;
• Or, in the case of Economic Development
and Civil Defence Emergency Management, where there is
recognition that current efforts across the region need to
be enhanced.
This provides the initial scope of regional
council functions and activities. In the future, work could
be undertaken to assess further functional transfers against
the principles agreed in the regional governance project.
The transfer would need to satisfy certain criteria set out
in legislation. This process should identify the
quantifiable costs of reform and savings achieved by
reducing duplication and transactions inherent in fragmented
delivery.
Figure 1: Strengthened Regional Council
This future work should
focus on the following functional areas which involve
activities undertaken by a range of other
agencies:
• Transport responsibilities;
• Water
responsibilities;
• Economic development;
• Urban
renewal.
Water and transport infrastructure are key
strategic assets that provide for the day-to-day health and
well-being of the people of the region. They are also key
public investments that shape the nature and form of our
city-region. Given the significant and legitimate public
concern over the strategic and public importance of both
transport and water infrastructure it is of fundamental
importance to have stronger provisions securing public
ownership of these assets than is provided for in the LGA
2002.
The potential for a regional role in urban renewal
is new and discussed separately below.
5.3 Transition and
transfer of functions and responsibilities
The magnitude
of the change involved is potentially very far reaching. It
is desirable that as far as possible, candidates standing
for office in the October 2007 elections have a clear
understanding of the expected scope of the strengthened
regional authority and the mechanism by which change would
occur. On the other hand, while the case for some of the
reforms is already compelling, significant further work is
required before many of the changes that could be desirable
can be finally decided upon. It is essential that adequate
time be provided for this work to be done properly, while
maintaining the momentum for change and a process that
ensures necessary decisions will be made. Further, once
reforms have been decided on, it is key that they be
implemented in a way that ensures the achievement of the
benefits sought.
Accordingly a staged change process is
recommended. The first stage would establish the
strengthened regional authority with a breadth of functions,
which could be at a later stage be built on with the
transfer of related functions from territorial authorities
and/or central government, if this is considered desirable
once having gone through a legislated investigation process.
This first stage would require legislation to be passed
prior to October 2007 to:
• Put in place the first set
of reforms to create an enhanced regional authority
undertaking the existing functions of the ARC, including
governance of ARH and ARTA, plus:
- Ownership and
governance of Watercare Services Ltd;
- The powers to
levy a regional fuel tax to fund transport, and regional
development contributions for growth related regional
infrastructure.
• Remove any legislative barriers to
effective regional decisions and action and to enable
voluntary further change. This would include amendment
of:
- The Transport Services Licensing Act and Land
Transport NZ passenger transport procurement rules;
- The
Local Government Auckland Amendment Act to enable the
Regional Land Transport Strategy to define projects and ARC
to govern ARTA subject to standard CCO provisions;
- The
relevant water legislation to enable Watercare ownership to
be transferred and to enable other future change;
- The
Local Government Act 1974 to provide status to the Regional
Sustainable Development Forum in place of the Regional
Growth Forum.
• Establish a framework that provides the
opportunity for the region to explore whether further reform
by way of transfers and vertical integration of the
functions identified above (transport, water, economic
development, urban development) is desirable. This
legislation would signal:
- The scope, process and
timetable for investigating further reforms and reporting to
central government for decision;
- The criteria that
would need to be satisfied in order for a transfer to take
place (based on the governance principles);
- That
transfers can be completed without residual liabilities and
without tax consequences;
- That as responsibilities
shift from one agency to another their respective rates take
is seen by the public to decrease and increase by the cost
of the responsibilities that are transferred. Any transfer
of rating burden must be fiscally neutral;
- A set of
principles to ensure that any transfers not be frustrated by
unreasonable behaviour.
• The first stage would also
involve some non-legislative actions such
as:
- Establishing a Regional Sustainable Development
Forum, with representatives from all the local authorities,
to develop ‘One Plan’ for the Auckland
region;
- Enhancing AucklandPlus’s functions to take on
activities recommended by the Metro Project Action
Plan;
- Investigating establishing the new regional urban
renewal function;
- Investigating shared services, for
example rates billing.
5.4 Regional Sustainable
Development Forum
A proposed new Regional Sustainable
Development Forum would be used to provide an effective
interface for central, regional and local spheres of
government.
Like the current Regional Growth Forum, it
would be a statutory standing committee of the strengthened
regional council. It would involve representation from all
councils in the Auckland region (similar to the existing
RGF). The Regional Sustainable Development Forum would
develop a single sustainable development plan for the region
that delivers a vision, and the actions required to achieve
it, across all dimensions of well-being (environmental,
social, cultural and economic). This One Plan for Auckland
would bring together into a single vision, a set of
objectives, goals and targets already articulated in
existing regional strategy documents, but placed within a
sustainable development framework. It would also need to
address gaps where significant regional issues are not
currently being addressed.
The role of the Regional
Council’s subsidiary delivery agencies would be to give
effect to the One Plan for Auckland.
The Regional
Sustainable Development Forum would replace the existing
Regional Growth Forum and its creation would result in the
repealing of existing Growth Forum provisions (LGA 1974
(1998 amendment no 89)).
5.5 Transport – RLTS and
ARTA
The proposed ARC response is firstly to improve
democratic decision-making by seeking changes that enable
the RLTS to identify strategic projects and to bring the
governance of ARTA in line with standard CCO provisions.
Secondly, to improve services to the Auckland public, there
is a need to further integrate public transport
infrastructure into ARTA. The ARC also supports retaining a
Regional Land Transport Committee.
The RLTS is the
primary vehicle for democratic decision-making about the
future of the Auckland’s transport system, but without the
ability to include strategic projects it has caused
unnecessary confusion and duplication at the ARTA/TA level.
The Auckland only restriction (section 36, LGAAA 2004) makes
the Auckland RLTS different from those of other regions for
no apparent reason. Some projects are of fundamental
strategic importance to the region, and need to be specified
in the RLTS to ensure the integration of land use and
transport and the range of outcomes intended. This is
especially important to signal to other agencies (i.e.
Transit and Central Government) the preferred regional
approach. This simple change would provide multiple
benefits.
Making ARTA subject (as far as possible) to
standard CCO provisions will improve public accountability
for the use of public funds and provide further incentives
for performance. The ARC provides ARTA with over half of its
rates funding and almost all of the funds generated by ARH.
The LGA 2002 holds the ARC accountable to the public for the
use of these funds. The existing provisions place ARC in the
position of having political accountability and funding
responsibility for ARTA but with limits on its ability to
govern.
Despite the intent of the LGAAA the region has
not yet been able to integrate public transport
infrastructure into ARTA. The transition of ARTNL assets
and functions into ARTA is not yet complete, and the
Government’s decisions relating to the role of OnTrack
have continued a multi-organisation approach to the delivery
of the rail system in the region. The experience in dealing
with ARTNL assets and functions shows that negotiated
transfers are extremely difficult to achieve even when the
key organisations agree on the broad principles of the
change.
Further integration of public sector public
transport infrastructure could considerably enhance the
development and delivery of the public transport system and
the seamless delivery of services to the public. The
further integration of transport responsibilities within
ARTA could provide real opportunities to implement the RLTS
in a meaningful way and could lead to genuine regional
priorities for transport investment and the integration of
land use and transport decision-making.
Accordingly, it
is considered that transport function is a key area that
requires further exploration through a future reform
process, supported by legislation, as outlined above.
Lastly, it is proposed that the funding capability of
the strengthened regional council should be enhanced by the
ability to utilise a regional fuel tax and regional
development contributions under the LGA
2002.
5.6 Water
As a first step to a more regionally
integrated approach to the provision of water services and
infrastructure investments, the ARC proposes the return of
Watercare to regional ownership and governance. Further
integration could then be considered through the staged
reform process outlined above.
ARC already has a position
that signals its support for Watercare returning to regional
ownership and governance under the ARC. Returning Watercare
to regional governance will provide stronger, broader and
more certain oversight than can currently be achieved
through the current fragmented ownership by the company’s
customers, including the ability to foster both
environmental and cost minimisation objectives. It provides
the ability to achieve stronger links and alignment between
water infrastructure investment decisions and urban form
through the RGS. The reform will create the framework for
more efficient pricing of water services and as a
consequence more environmentally and economically
sustainable infrastructure decisions. This includes the
ability to deliver both large scale infrastructural
solutions and demand management, reuse, smaller-scale
community based investment with supporting use of economic
incentives/pricing mechanisms.
There has been
considerable work over many years suggesting that there
could potentially be significant savings that could be
achieved from the vertical integration of water management
within the region. The Parliamentary Commissioner for the
Environment has presented a compelling case for integrated
management of the three waters in order to deliver sound
environmental and sustainable development outcomes.
Consequently, it is considered important that water
responsibilities within the region are given further
consideration through the future reform process outlined
above.
5.7 Economic development
The proposed ARC
response to improve regional level coordination and
facilitation through an enhancement of Auckland Plus, to
take on coordination of economic development activity across
the region, and the delivery of the innovation, skill,
regional brand and investment attraction components of the
Metro Action Plan.
The ARC as the lead agency in the
partnership based Metro project, is now in a position to
build on the wide public interest and engagement in the
Metro Action Plan, and to now focus efforts on achieving
successful implementation that builds on the energy, spirit
of cooperation and aspirations that Metro has generated. The
shift to establish a stronger regional delivery agency for
economic development in Auckland would also reflect the
comparative success of the Canterbury Development
Corporation and recent moves in Wellington to consolidate
regional economic development delivery within the Wellington
Regional Council.
The enhanced regional Economic
Development Agency could become a subsidiary of the ARC and
would be required to give effect to the region’s
sustainable development plan and regional economic
development strategy. Enhancing existing arrangements will
generate a number of benefits, including improved
coordination and delivery at the regional level that
overcomes existing fragmentation and a lack of alignment,
along with an enhanced ability to secure external funding
from central government and the private
sector.
5.8 Potential regional role in urban
renewal
The ARC supports further consideration of a
regional role in urban renewal and the potential for a new
urban renewal agency to be established. The underlying
premise for a new regional role in urban renewal would be a
strong commitment to sustainability, this means a commitment
to demonstrating excellence in achieving environmental
standards and by stimulating innovation and quality outcomes
in design and construction, while building on the compact
city approach. It also includes consideration of ways to
include improved social outcomes through urban development.
Further work is required to clarify the objective of the
regional level of involvement, including what the regional
agency could offer that is distinct from other parties, and
the relationship between the regional function and the
property corporations already operating at the local
authority level. There are also strong connections with the
waterfront redevelopment.
It is increasingly recognised
that one of the key policy areas where the existing local
government framework has failed is in the implementation of
the RGS. In addition to deficiencies resulting from an
over-reliance on regulatory approaches, the market has
struggled to deliver sensitive and comprehensive urban
renewal. Redevelopment within the MUL has tended to be
infill, or focused on sites that have become available and
been developed despite potentially negative impacts on the
surrounding community and neighbours. Work on both the
monitoring of the implementation of the RGS and its current
review shows that one of the biggest impediments to
appropriate intensification is the inability to aggregate
titles to provide for comprehensive re-development.
New
approaches are needed including a greater ability to achieve
land use changes that reinforce public transport investments
that can shape and influence design and development outcomes
‘on the ground’.
The proposed response is to further
explore a regional role and mechanisms that enhance the
regional council’s ability to achieve high quality,
sustainable urban redevelopment. This in turn will provide
for a more comprehensive and integrated approach to
development, along with an enhanced capability to implement
regionally significant projects. Further consideration is
needed to facilitate comprehensive and sensitive
redevelopment by way of overcoming land fragmentation
through aggregating titles (through for example providing
the Regional Council with powers of compulsory purchase for
urban renewal (under defined criteria) that were available
to TAs under the LGA 1974 but were repealed with the passage
of the LGA 2002).
5.9 Regional amenities
The ARC
recognises that there are funding issues and a number of
complications around the ownership and governance of a
number of facilities and organisations that provide
recreational, cultural and other benefits to the regional
community.
The ARC is concerned that there are
significant risks for ratepayers whilst the criteria to
define ‘regional’ in the context of regional facilities
and amenities remains ill-defined and ambiguous. There may
be an unrealistic expectation amongst certain venues and
groups that they will receive substantially more money in
contributions from ratepayers. Any new or enhanced role for
the regional council therefore requires careful
consideration and a commensurate shift in funding for the
facility or amenity from the local level to the regional
level.
The ARC would be concerned to ensure that any
changes result in providing higher quality services and
opportunities to the people of Auckland and service delivery
aligned to agreed regional priorities, whilst minimising the
potential impact on ratepayers.
5.10 Representation
The ARC’s position is that the
representation arrangements for the enhanced Regional
Council be those currently applying to the ARC, including a
Chairman elected by the Council, as per Schedule 7 LGA
2002.
The ARC has just been through a constituency review
that favoured the status quo with a close link to TA
boundaries. The ARC’s review demonstrated that the status
quo arrangements work well and enable the effective
representation of both rural and urban communities in
decision-making.
5.11 Establishment
The ARC’s
position is that the enhanced regional entity should be
established from the existing ARC with the retention of its
existing name. A complete disestablishment / establishment
process for the ARC would be excessive and would have a
profound effect on the ability to continue to deliver during
the transition process. Such an approach would generate
significant costs and disruption.
5.12 Other matters
Shared Services
The ARC strongly supports looking at
ways to improve consistency through the provision of shared
services across the region. The ARC considers that this
provides a major opportunity for cost savings and
efficiencies that will benefit the ratepayers and public of
Auckland. The reform project should consider legislation to
support a shared services approach. A key opportunity for
improvement is the delivery of a single property valuation
system and billing system for rates across the region.
Inclusion of Franklin District Council
Franklin
District Council is currently split between the Auckland
region and the Waikato region. For transport, civil defence
and economic development purposes the south of Franklin is
dealt with as part of the Auckland region, but for all other
purposes it is part of the Waikato region. The main reason
for the south of Franklin to be part of the Waikato region
is flood management, however, in many other respects the
south of Franklin is increasingly exposed to the same sort
of peri-urban pressures that affect the north of Franklin,
rural Manukau and Rodney. It is suggested that, to further
integrate management and to deliver administrative
simplicity, the whole of Franklin district be included in
the Auckland region.
Civil defence emergency management
(CDEM)
Recent reviews have highlighted the existing
arrangements are not working effectively and compromise the
ability to deliver a well-coordinated regional emergency
response. To address these concerns it is proposed that
Civil Defence Emergency Management and regional emergency
response become a responsibility of the stronger regional
entity.
The benefits of this change would be to deliver
a more effective regional emergency response, provide a
clear responsibility and mandate and address the
shortcomings of the Civil Defence Emergency Management Act
2002. The change is likely to reduce transaction costs that
result from the joint provision of a CDEM response by 8
local authorities.
6. PUBLIC CONSULTATION
The small
window of opportunity provided by the central government
legislative timetable and next year’s local body elections
have placed significant constraints on the potential reform
timetable. This has consequences on the scope and timing of
public consultation in the policy development process.
There have been two regional fora with elected
representatives across the region. There has also been
initial discussion with iwi on the governance project.
It is important to note that the ARC will not have an
ultimate decision-making role in this process – that is
subject to the discretion of Central Government. Central
Government will ultimately decide on the role, function,
strategic asset and service delivery implications for all
local authorities in the Auckland area. The ARC will be in a
position to consult and to undertake a special consultative
procedure once the intentions of central government are made
clearer. This would form an important part of preparing the
ARC submission to any Select Committee process on any draft
legalisation central Government may propose – and at that
point in time the ARC will be in a position to have a
detailed proposition that communities will be able to
respond to.
However, as noted in an earlier report the
ARC is committed to ensuring as open and inclusive a process
as possible is undertaken, within these constraints. Council
has resolved to hold an additional Council meeting in
advance of the ARC making final resolutions on its position
to facilitate public input.
A meeting has been convened
to hear public feedback on the ARC’s regional governance
proposals on Saturday 25 November at the Auckland Regional
Council. To support this process, this paper and the
resolutions from 8 November Council meeting will be made
broadly available to interested parties and the public.