Transpower welcomes project decision
Media release
25 May 2007
Transpower
welcomes Notice of Intention to approve its Otahuhu
substation diversity project
Transpower has welcomed the Electricity Commission’s Notice of Intention to approve an investment plan that will modernise the Otahuhu substation and provide greater security and diversity of electricity supply to Auckland.
The Electricity Commission today advised Transpower of its Notice of Intention to approve its proposal. The proposal includes building a new physically separate, enclosed, high reliability 220 kV switchyard on the Otahuhu site.
Chief Executive Dr Ralph Craven said Transpower has responded to concerns about Auckland’s heavy reliance on the existing substation equipment at Otahuhu.
“This is a significant investment that addresses historical issues. For many decades Otahuhu substation has been the key link in the network, where electricity comes into Auckland from the south and is then distributed throughout Auckland and Northland. However, the Otahuhu facility is ageing and is in need of some additional equipment.”
“The current design of the substation evolved between the 1930s and the 1960s. Currently there are 110 kV and 220 kV outdoor switchyards located side by side and the switchyards are at risk for high impact, low probability events. By providing a separate, new technology switchyard, it will significantly reduce this risk and improve reliability of supplies into Auckland,” Dr Craven said.
The power outage of 12 June 2006 occurred when an earthwire fell across one of the busbars. This is an example of a high impact, low probability event.
Dr Craven said that this project is an important step in a long-term strategy to provide much improved diversity of supply into and across Auckland. “It is also consistent with the objectives of the Government Policy Statement on Electricity. This policy supports investments that provide resilience against the effects of high impact, low probability events and that provide diversity to larger load centres.”
Transpower had planned to upgrade the Otahuhu substation by 2011 as part of the proposal to build a new transmission line from Whakamaru to south Auckland. That line is now proposed to terminate at Pakuranga substation, further improving diversity of electricity supply into Auckland. The Otahuhu substation development proposal was submitted separately for approval to the Electricity Commission. Transpower intends to commission the new facilities at Otahuhu by the end of 2009.
For more
information:
Rebecca Wilson, Communications Manager; 04
498 2695; 021 578 608
Questions and Answers on the Otahuhu Diversity Project
What is the justification for
this project?
Transpower considers this project to be an
urgent reliability upgrade to reduce the possibility of high
impact, low probability events disrupting power supplies to
the Auckland area. The existing substation configuration is
not up to current international best practice for a major
load centre.
How much will the upgrade at Otahuhu
substation cost?
The estimated capital cost is $83m in
2006 dollars, including contingencies ($75m excluding
contingencies). This represents the maximum cost that
Transpower will be seeking to recover. Transpower will only
recover the actual costs if they are lower than $83
million.
What does the project include?
New indoor
220 kV gas insulated switchgear (GIS), physically separate
from the existing outdoor switchyards
Underground
cable for all transmission line entry and exit
points
Reconnect half of the existing 220 kV circuits
to the new switchyard
Underground cable connections
between the new and existing switchyards
What is Gas
Insulated Switchgear (GIS)?
GIS technology has been
preferred over air insulated switchgear (AIS), which is
currently used at Otahuhu. GIS has a higher capital cost but
has a number of advantages:
GIS is much smaller than
AIS and greater physical separation can be achieved from the
existing equipment
GIS is housed indoors, in a
building similar in size or possibly smaller than the
existing warehouses on the Otahuhu site
As the GIS is
fully enclosed it is a controlled environment that is more
protected from outside influences
Using GIS will
leave room for future upgrades at the Otahuhu site.
How
does this project fit into a strategic long-term plan for
Auckland’s electricity supply?
There are two important
projects that will impact on the medium-term (5-6 years)
development at Otahuhu substation:
A new high
capacity transmission line into Auckland from the
south
Enhanced supply across Auckland
At Otahuhu
substation these developments will require new connections
for additional incoming and outgoing circuits, new
transformers and voltage support equipment. In the
longer-term, Transpower intends to replace the existing
outdoor switchyard with modern new equipment.
What
approvals are needed?
The Electricity Commission has
issued its Notice of Intention to approve the project.
Transpower owns the land at Otahuhu substation but some
consents may be required from the Manukau City Council, with
whom initial discussions have been held.
How long will it
take?
Transpower intends to commission the new facilities
at Otahuhu by 2009.
Ends