Boost to New Plymouth’s security of electricity supply

The successful completion of an electricity supply upgrade for New Plymouth is being celebrated today by Transpower, owner and operator of the National Grid, and local lines company Powerco.

Two new transformers have been installed at Transpower’s New Plymouth substation in Carrington Street. As part of the project, other substation equipment including a new switchboard, has also been upgraded.

The $9 million, eight-month project has substantially increased the capacity of the Carrington Street substation. The previous transformers each had a rating of 60 MVA. The new transformers each have a rating of 75 MVA and will meet projected load growth in the New Plymouth area up to, and beyond, 2030.

Transpower’s GM National Grid David Laurie said the works undertaken will help to increase security of supply to the New Plymouth area.

“The completion of the project is the culmination of Transpower and Powerco working together to determine an effective solution to meet the increasing New Plymouth load.”

Powerco Network Asset Strategy Manager Michael Whaley said the project represented a significant investment in the local electricity infrastructure.

“Powerco is committed to ensuring the region’s electricity infrastructure provides a solid platform on which the local economy can continue to grow.

“This project sends a positive message to businesses looking to expand in or move to the New Plymouth district – the region is well placed to accommodate future growth. The energy infrastructure is already in place and future-proofed for at least the next 20 years.”

Advertisement - scroll to continue reading

David Laurie said implementation of the project went very smoothly. “Good project planning and the skill of the contractors meant no unplanned disruption to end users occurred during the upgrade.”

The principal contractor for the project was Electrix, with considerable input from Tenix. The main equipment suppliers were Wilson Transformer (transformers) and ABB Switchgear (switchgear).


ends

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.