Busway Traffic Bulletin August 4-10

 

Auckland Regional Office

                                             

3 August 2007

 

BUSWAY TRAFFIC BULLETIN: SATURDAY 4 TO FRIDAY 10 AUGUST

 

Transit New Zealandadvises motorists of next week’s proposed closures for work on State Highway 1 for Northern Buswayconstruction (weather permitting).

RAMP AND LINK CLOSURES:

ONEWA RD

Sunday 5 & Monday 6 August(contingency closure)

Onewa Rdsouthbound on-ramp closed overnight from 10pmuntil 5amthe following morning to allow for a traffic switch

·      Diversion via Esmonde Rd southbound on-ramp

·      This closure will only take place if weather postpones earlier planned works 

 

Sunday 5 – Tuesday 7 August (contingency closure)

Onewa Rdeastbound closed from 10pmuntil 5amthe following morning for island removal

·      Sylvan Ave north and southbound will also be closed

·      Diversion via Lake Rd

·      This closure will only take place if weather postpones earlier planned works 

 

ESMONDE RD

Monday 6 August (contingency 7 August)

SH1 Esmonde Rdnorthbound on-ramps closed from 9amuntil 3pmthe following morning for catch pit repairs

·      Diversion via Northcote Rd northbound on-ramp

 

TRISTRAM AVE

Sunday 5 – Thursday 9 August (contingency closure)

SH1 Tristram Avesouthbound off-ramp closed from 10pmuntil 5amthe following morning for barrier removal

·      Diversion via Northcote Rd southbound off-ramp

·      This closure will only take place if weather postpones earlier planned works 

Advertisement - scroll to continue reading

 

CONSTELLATION DR

Sunday 5 August (contingency 6 – 8 August)

SH1 Constellation Drsouthbound on-ramp closed from 10pmuntil 5amthe following morning for barrier removal

·      Diversion via Tristram Ave southbound on-ramp

The above include contingency dates and diversion routes, which are subject to change. Work planned for adjacent junctions will be reviewed daily to ensure that no two consecutive over bridges or interchanges are closed at the same time and the correct diversions are in place.

Road users are requested to use the signposted detours whilst the closures are in operation.

Transit New Zealandapologises for any inconvenience caused.

 

ends
 

 

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.