Auckland Transport set to deliver final stage of Glenfield Road upgrade
Work on the final stage of Auckland Transport’s $40 million Glenfield Road upgrade is due to begin early next year.
Glenfield Road is a major arterial road serving the north of the city with more than 30,000 vehicles using it each day. Auckland Transport estimates that this figure will rise by approximately 3% per year.
The project, which began under the former North Shore City Council, aims to increase traffic capacity, ease congestion and improve pedestrian and cycle safety. Work has been undertaken in four stages in order to minimise disruption to residents and commuters.
Stage four is the final link in the upgrade which will focus on the section of Glenfield Road between James Street (South) and Sunset Road. It will release all of the benefits from the different stages of the project and will join up to future improvements on Albany Highway.
The final stage will take approximately two years to complete and will involve the following:
• Widening of Glenfield
Road to provide two lanes in each direction
• Changes
to the Wairau/Glenfield Road intersection
• Road
resurfacing
• Safer crossing points for pedestrians
with tactile markings for those with a visual
impairment
• Widening of footpaths
• 1.5m wide
on-road cycle lanes in both directions
• New raised,
planted and flush painted medians to improve
safety
• Indented bus bays
• Bus priority measures
at intersections to improve travel times
• Landscaping
and retaining walls
Diversions will be in place during the construction period but Auckland Transport will make every effort to ensure that disruption is kept to a minimum. Details will be advised in advance to residents and commuters.
The first stage of the Glenfield Road
upgrade concentrated on the Sunset/Glenfield road
intersection. Priorities were to increase vehicle capacity,
add additional lanes and improve underground
services. Stage two saw improvements to the section
between Bentley Ave and Camrose Place which
included: During stage
three, the section of Glenfield Road between Camrose Place
and James Street (south) was widened to provide two lanes in
each direction. The Hogan/Manuka Road intersection was also
upgraded. About Auckland
Transport
NOTES TO THE
EDITOR
• The installation of two lanes in each
direction
• The installation of raised planted
medians
• Intersection upgrades
• New on-road
cycle lanes
• Widening of
footpaths
• Undergrounding of utility
services
• Road surface upgrades
Auckland Transport is responsible for
all of the region’s transport services (excluding state
highways) - from roads and footpaths, to cycling, parking
and public transport.
Among its main tasks are:
To design, build and maintain Auckland’s roads, ferry
wharves, cycleways and walkways.
Co-ordinate
road safety and community transport initiatives such as
school travel
Plan and fund bus, train and ferry
services across Auckland.
For more
information go to www.aucklandtransport.govt.nz.