SCIRT traffic update Wednesday 25 September – bridge reopening, Antigua two way again
New Brighton Road short term closure Friday 27 September: New Brighton Road at Bower Avenue closed 9 am to 3 pm, for the long pipe to be pulled off New Brighton Road and onto Bower Ave.
South Brighton’s Bridge St bridge: reopening to two-way traffic from this Friday, 27 September, by 3pm.
Heathcote/ Opawa bridge third closure this weekend from 6 pm Friday to 6 am Monday: See earlier story and works notice. http://strongerchristchurch.govt.nz/article/heathcote-river-opawaho-highway-bridge-final-repairs-involve-weekend-closures This is the third weekend closure and the work on the abutments is going well.
Shirley night works around the Palms shopping centre: SCIRT night works started this week in Marshland, Shirley and New Brighton Roads 7 pm to 7 am, installing the new vacuum wastewater system. This work will take just over two months to do. Because these new pipes criss-cross the road, this work can only be done at night when traffic volumes are low. Each crossing will take up to four nights to complete. Road users will see extra lights around these work sites. http://strongerchristchurch.govt.nz/work/activity/3629
Centaurus Road, Huntsbury: SCIRT’s City Care team is working on Centaurus Road from 30 September until mid November – from the Wilsons Road/Centaurus Road roundabout towards Ramahana Road. On-street parking will be affected. Two–way traffic in place but manual traffic system at times. This is a busy area for cyclists, school children and pedestrians, near a café, so care is needed by road users. http://strongerchristchurch.govt.nz/work/activity/3611
Antigua St, Sydenham, is open for two way traffic from today: The Antigua/Brougham St intersection has been one way only for some time. Drivers will once again be able to turn onto Antigua St from Brougham St.
Central city new
work
Manchester St central city,
Salisbury to Peterborough St: This block will be
closed to through traffic for two weeks for wastewater
trenching. Residents’ access to the street will be
maintained.
Salisbury St, central city, between Durham St North and Colombo St: Salisbury St, a one-way eastbound street, will be down to one lane in this block until mid December for manhole work and a deep trench (three metres) for a wastewater trunk main pipe. http://strongerchristchurch.govt.nz/work/activity/3623
For earlier traffic update with more information across the city: http://strongerchristchurch.govt.nz/article/scirt-traffic-update-for-week-starting-23-september-2013