Key recommendations from the Committee of the Whole
Key recommendations from the Committee of the Whole
Christchurch City Council's Earthquake Recovery Committee of the Whole met yesterday. Following were the key matters considered and recommendations the Committee will make to the Council:
Sumner Road reinstatement work
endorsed to begin this year
The Committee has endorsed
the recommendation to the Council later this month to move
forward with the rebuilding work of Sumner Road. Sumner
Road, between Evans Pass Road and Summit Road, has been
closed to all traffic since the February 2011 earthquake on
the grounds of safety due to unstable rocks and
slopes.
The reinstatement of the route is expected to take eighteen months and cost $40 million dollars, which has already been budgeted for in the Christchurch City Three Year Plan. Upon expected completion by the end of 2016, the route will be returned to a pre-quake level of service. The next stage of the process will be the public engagement feedback phase.
Red zone revaluations extension
The
Committee recommended a 10 day extension of the deadline for
objections to rating revaluations in the red zone. This
means owners of red zone properties have until 12 May 2014
to lodge objections. The extension is effective immediately
and will be ratified by the Council at the next meeting on 8
May 2014. The decision to extend the objections period
follows an approach from the Human Rights Commission which
was concerned about the impact of the revaluations on red
zone properties and the stress this had caused
owners.
Affordable and social housing consultation process
to be considered on 12 May
The Committee asked staff to
develop a Statement of Proposal for public consultation in
the areas of affordable and social housing for consideration
at a 12 May Council meeting.
The Council is considering
becoming involved in the provision of affordable housing and
is re-evaluating the future ownership, management and
development of its social housing portfolio.
The
Committee also asked staff to provide advice to the 12 May
Council meeting on a consultation process to be carried out
on the draft Christchurch Housing Accord it recently signed
with the Government.
Rates remission policy to be reviewed
to assist those affected by recent floods
The Committee
has recommended staff develop rate remission criteria to
apply to households affected by flooding and land movement
caused by flooding. The report will also cover the timing of
the implementation of the new criteria and it will go to the
Council for decision by the end of May.
Majestic Theatre
update
Following the meeting of the Earthquake Recovery
Committee on 3 April 2014, staff requested urgent advice is
obtained on the implications of the Council's position on
the Majestic Theatre demolition. Christchurch City Council
officials and Warwick Isaacs, Director of Central
Christchurch Development Unit (CCDU) then met to discuss the
issues and advice on 3 April 2014.
Following this meeting, there was subsequent correspondence and having considered all advice, the Council has decided it is clear there are no grounds for a successful judicial review application to the High Court to overturn CERA's section 38 notice and halt the demolition of the Theatre.
Transport projects
update
The Committee will recommend to the Council that
it gives the go-ahead to begin work on transport projects
needed to support the Anchor Projects and approval to engage
with the public and stakeholders over the design concepts of
the initial suite of 'First Phase Projects'. This work is
designed to align with SCIRT programme wherever
possible.
Staff have been working through the details of the projects in the Christchurch Central Recovery Plan (CCRP) and have recommended amendments that two projects be deferred and four projects added.
To view the projects
please visit the website by clicking here The
extra projects are required to support the Bus Interchange
and need to be in place by April 2015. They include: It is
recommended that one project be deferred (for more
information click here The
Committee will recommend the Council begins public and
stakeholder engagement on the design concepts for each
project. The indicative cost of this first phase is $72
million dollars with an additional $4 million for bus super
stops that will be funded separately. As part of this
report to the Council, staff have been requested to provide
advice on how work on Kilmore and Salisbury streets can be
brought forward in line with community aspirations and SCIRT
repair programme.
*
Tuam Street from Durham to Madras streets (Project 9)
* Lichfield Street from Manchester to Oxford streets
(Project 10)
* Colombo Street from Hereford to St
Asaph streets (Project 11)
* Establishing a 30
kilometres per hour speed limit environment.
- Ends
-