Flooding Taskforce mitigation work continues across the city
Tuesday 13 May 2014
Flooding Taskforce mitigation work continues across the city
The Council contractors were out first thing this morning, continuing with the ongoing flood mitigation work following yesterday's approval of the range of short term flood prevention measures recommended by the Mayoral Taskforce for Flooding.
Mayor Lianne Dalziel says that we are wasting no time in getting on with short term solutions.
"The flood mitigation work is happening right now with work starting in prioritised areas of Christchurch to improve flood protection and management.
"Members of the Taskforce team have met with contractors and consultant engineers this morning to discuss the concept design of a temporary pump-station for the Flockton/Dudley Creek area.
"The team are contacting homeowners whose properties are considered to be in the 'Level One' category to discuss what options best suit their current circumstances. The team has also identified specific work in the flood-prone areas and directed contractors to focus current maintenance services in these locations.
"It is very important that households who have experienced serious flooding contact the Council so we can ensure they are included on our database and speak to them about the short term flood mitigation options in their area.
The Council is planning a schedule of community meetings and will be contacting residents early next week with the details of times and venues. At these meetings Council staff will discuss what will be happening in each of the areas.
Work happening right now:
Sediment removal - Dudley Creek:
Contractors (two
excavators) are moving downstream from Slater Street,
removing sediment from the creek's sides. They are removing
approximately 400 millimetres along this bank. This same
section of the creek was dug out to the gravel base in
May/June of last year. The crews should be moving on to
Julius Terrace today and will continue on down Stapletons
Road.
Vegetation removal - Dudley Creek:
Vegetation within the channel that is either causing
blockages or is compromising the channel width has been
taken out ahead of the sediment removal.
Tree
removals - Dudley Creek:
A large willow tree
partially within the waterway was removed yesterday from a
Chrystal Street property. The Council's tree removal team
will spend the rest of the week in Banks Avenue removing
trees identified as being a restriction or within channel
widening areas.
Bank modification - Dudley
Creek:
Contractors should be starting later this
week on bank modifications along Banks Avenue (Council-owned
land) to open up the waterway channel.
Sump and pipe
jet cleaning - Lower Heathcote:
Council contractors
are cleaning sumps, pipes and flap-gates in Clarendon and
Richardson Terraces.
Surveying - Shirley:
The Council survey team is working on establishing
property/stream boundaries along Banks Avenue and North
Parade. The Council's property team is about to start
discussions with property owners regarding boundaries that
may be affected by channel widening and/or vegetation
removal. This information will help with clarification so
work can begin.
The Mayoral Taskforce on Flooding was set up two weeks ago to fast-track work to identify the causes and possible short term solutions available to householders experiencing repeated flooding.
In total, the Taskforce has so far pinpointed nearly 1000 Christchurch properties that have been subject to some form of flooding impact in the post-earthquake environment, with the 56 most vulnerable properties flooded inside the home two or more times since the 2010/2011 earthquakes. Further surveys and engagement with residents is likely to change the current total of properties impacted.
Flood impact analysis categories:
Level One: Two or more instances of flooding of dwelling floors since the earthquakes - 56 properties.
Level Two: Two or more instances of flooding under dwellings since the earthquakes - 471 properties.
Level Three: Two or more instances of flooding restricting resident access to dwellings since the earthquakes - 487 properties.
The Taskforce's report to
the Council, the draft technical report and a map detailing
the flooding analysis in the post-earthquake environment can
be viewed on the Council website at www.ccc.govt.nz/floodmitigation For
further information, please call the Customer Call Centre on
(03) 941 8999 or 0800 800 169 or email queries to
floodmitigation@ccc.govt.nz
- Ends
-