Community flood meetings commence as mitigation work goes on
21 May 2014
Community flood meetings commence as mitigation work continues
Community meetings in flood affected areas start tonight, with Little River residents able to learn more about proposed mitigation measures.
Throughout the next week engineers from the 18-strong Mayoral Taskforce for Flooding will front community meetings throughout the city, giving residents an opportunity to feedback and ask questions on the flood protection measures planned for their area.
The Taskforce’s technical report, released last week, contains detailed area reports and flood mitigation measures specific to the relevant catchment areas. The technical report including appendices A and B, can be viewed on the Council website at www.ccc.govt.nz/floodmitigation
Click here for further information on the community meetings, including dates, times and venues.
The
Flooding Taskforce has divided into eight
teams:
• pumping
• bridging
• house
wrapping
• strengthening
communities
• dredging
• Council
resolutions
• local area
schemes
• maintenance.
Each team is focused on developing its own scope and a team approach to determine the costs and programmes of their activity.
Work has started on developing local area solutions in more detail, many of which will use a combination of mitigation activities.
Rates remission
A report
recommending 100 per cent rates remission for the most
heavily affected flood properties will be discussed at
tomorrow’s Council meeting. The report starts on page 263
of the agenda.
Further information will be made available following the Council’s decision.
Work currently underway:
Channel widening / bank modification
– Dudley Creek
Channel widening at Banks Avenue is
progressing well. A Council arborist has been on site to
advise on best practice for working around mature trees. The
current team will begin widening Dudley Creek opposite 70
Banks Avenue from Wednesday 21 May. Another crew will start
work along Banks Avenue before Friday.
Sediment removal
– Dudley Creek
Sediment removal is continuing in
the top section of Dudley Creek. The crew is at the end of
Julius Terrace today and will move into Stapleton’s Road
tomorrow.
Work completed this week:
Sediment removal – Dudley
Creek
Approximately 300 millimetres depth of sediment
has been removed from the channel through Julius
Terrace.
An estimated 100 cubic metres of sediment has been removed so far, excavated from the creek bank downstream of the Hills/Shirley shops to Chancellor Street. This will allow for a faster flow within the creek.
Surveying – Shirley
The Council’s
survey team has completed site work at the properties
assessed as a priority for widening/maintenance. Schemes are
being drawn up for the Council property team to discuss with
impacted owners.
Ongoing work:
Council staff and
contractors are continuing to speak with local residents on
the extent of the work planned in the Dudley Creek
area.
Targeted information database
The
Taskforce is continuing to update its contact information
database for all affected residents in the identified
flood-prone areas. Once complete, this will allow the
Council to relay up-to-date information to residents about
flood mitigation work in each area, weather updates,
temporary traffic management plans and other associated
details.
To be included on the database, residents can forward their contact details to the Council by email at floodmitigation@ccc.govt.nz. They can also call the Customer Call Centre on (03) 941 8999 or 0800 800 169 and leave their contact information with a member of staff.
For further information on flood mitigation work, residents can call the Customer Call Centre on (03) 941 8999 or 0800 800 169 or email queries to floodmitigation@ccc.govt.nz
ENDS