SCIRT traffic update
SCIRT traffic update, week starting Monday 13 July 2015
Central city
update
Moorhouse Ave
overbridge
• The U-turn bays under the Moorhouse
overbridge will be closed from Monday 13 July. This affects
traffic travelling eastbound that use the turning bay to
access the Harvey Norman Centre. Follow the signs to reach
the Harvey Norman Centre, which is open for business.
•
• Moorhouse Ave continues to have lane drops,
including the overbridge, so expect delays at peak times,
however flow is improving as work sites reduce.
Barbadoes St
Work on Barbadoes St will affect the Moorhouse Ave intersection for a few days with a lane drop. Use Fitzgerald Ave and avoid Barbadoes St or be ready for delays.
ends
Other central city streets
• Manchester
St is one-way southbound between Armagh St and Gloucester
St. Northbound traffic detours. Try to avoid during peak
hours.
•
• Colombo St is one-way northbound
between Moorhouse Ave and Lichfield St for most of the week.
•
• St Asaph St has a lane drop between Colombo
and Durham Sts.
•
• Gloucester St will be one-way
westbound, between Manchester and Colombo Sts for about a
week for wastewater repairs. The one-way system will be
lifted every afternoon during peak-hour traffic.
Be a Rebuild Hero
Please support businesses and shops affected by road works.
Thank you for going the extra mile for the rebuild.
Aranui/Wainoni
See
the latest Aranui map showing bus routes and
detours.
• Breezes Rd remains closed
to southbound traffic at the Pages Rd intersection until
Friday. Please follow the detour signs.
•
• Road
repairs start in Marlow Rd and
Doreen St on 20 July with one-ways in
place.
•
• Basingstoke St
-
Progressive road closures east of Bournemouth Cres, heading
towards Hampshire St for another month.
- A one-way
system is in place east of Portsmouth St to Bournemouth
Cres. Please be aware of changed traffic
conditions.
Work in other suburbs
Riccarton - Kahu Rd
Work continues in Kotare St and Kahu Rd for another week. Allow extra travelling time through this area.
Edgeware, St Albans
CCTV investigations will take place this week at night in St Albans and Edgeware, including Bealey Ave, Papanui Rd, Sherborne/Cranford Sts and Edgeware Rd. Please slow down around work sites.
St Albans
Edgeware Rd
There’s a one-way system for eastbound traffic on Edgeware Rd, between Manchester and Madras Sts for about a week, with no street parking.
Edgeware - Hills Rd
The one-way system for northbound traffic on Hills Rd (between Guild St and Dudley St) continues. A detour is in place for southbound traffic on Hills Rd. Follow the detour signs. Work is expected to finish at the end of July.
Burwood
• Lake
Terrace Rd is closed between New Brighton Rd and
Burwood Rd for one more month, expected to reopen
mid-August. Follow detour
signs.
•
• Mairehau Rd, outside Burwood
Hospital - This week, traffic will not be able to
turn right out of Burwood Hospital main entrance, or turn
right into the main entrance. Instead of turning right into
the hospital, continue to the intersection of Mairehau and
Burwood Rds, and use the roundabout to come back to the
hospital entrance.
Linwood – Wyon St, Buckleys Rd, Dacre St, Worcester St
• The intersection of Wyon St and Buckleys Rd will reopen mid-week (weather dependent). We will then close the intersection of Dacre St and Buckleys Rd for about a week.
• Worcester St is closed to eastbound traffic at Linwood Ave.
St Martins - Centaurus Rd
Temporary lane shifts and shoulder closures are in place along Centaurus Rd between St Martins Rd and Kowhai Tce for about two weeks. Two-way traffic will continue on Centaurus Rd, during this wastewater repair work.
Turning restrictions:
• No right turn out of Kowhai Tce onto Centaurus Rd
• No right turn onto Kowhai Tce from Centaurus Rd
• No right turn at the intersection of Centaurus Rd and Centaurus Rd.
Addington – Antigua St
Antigua St between the railway and Moorhouse Ave is expected to be closed to northbound traffic for a few days, from Monday. Follow detour signs.
Governors Bay – Dyers Pass Rd, Governors Bay Rd
The SCIRT work along Dyers Pass Rd to repair the retaining walls and resurface parts of the road is almost complete. The next stage is to repair the concrete stormwater channel on the odd-numbered (northbound) side of Dyers Pass Rd. Work begins Monday and will be finished by the end of July. Temporary traffic lights remain in place.
ends