SCIRT traffic update: Week starting 19/10/15
SCIRT traffic update: Week starting Monday, 19 October, 2015
GOOD
NEWS
• Residents and commuters in east
Christchurch will be pleased one of their main
thoroughfares, Breezes Rd, is this week
re-opening to two-way traffic between Pages Rd and Wainoni
Rd after more than 4 months one-way.
• Although
there is still some work to complete in Breezes Rd near the
Wainoni Rd intersection which will require another short
closure there, this is some weeks away.
• Also
the one-way section of Pages Rd is
shortening with the re-opening this week to two-way traffic
between Shuttle Dr and Shortland St.
MAIN ROADS -
expect delays especially during peak times
•
Barbadoes St, road rebuild works start on
Monday 19 October, for 8 weeks. The work is undertaken on
one side of the road at a time to allow two-way traffic. The
works are between 431 and 471 Barbadoes St near the Bealey
Ave intersection.
• Marshland
Rd between The Palms and 123 Marshland Rd is
undergoing road repairs. Two-way traffic is maintained but
reduced lanes may cause delays. Please look out for
pedestrians and cyclists.
• Papanui Rd
– between Innes Rd and Murray Pl has two-way
traffic maintained but has bus lane and cycle lane closures,
lane shifts and turning restrictions at the Innes
Rd and Papanui Rd intersection.
Please take care here.
There are many organisations rebuilding our Central City. Check the best way to get in and around the city at: www.tfc.govt.nz
SCIRT
in the Central City
•
Moorhouse Ave Bridge is down to one lane on
each side for another 3 weeks.
•
Fitzgerald Ave has reduced lanes between
Gloucester and Worcester Sts and between St Asaph St and
Ferry Rd for the next 4 weeks. Please consider alternative
routes at peak times.
• Manchester St
is one-way southbound between Hereford St and
Lichfield St.
Fendalton - major wastewater works
are soon to start in Holmwood Rd and Garden
Rd.
• Holmwood Rd
will be closed from Tuesday 27 October for 3 weeks for
reconnection of individual properties’ lateral pipes to a
new main wastewater pipe. Ithas been one-way westbound since
mid-September for replacement of wastewater pipes.
•
Holmwood Rd will revert to one-way westbound after the
lateral reconnections are finished.
•
Garden Rd will be closed from Tuesday 27
October for about 18 weeks for wastewater repairs. The
repairs are in 3 stages of about 6 weeks each. Keep an eye
out for signs which will confirm the dates closer to this
time.
Beach Rd, New Brighton – major
wastewater works underway
•
Beach Rd has a progressive road closure. A
section crew started last week just west of the shops at
Bower Ave and will progress for 3 months towards Effingham
St. The first stage, between 144 Beach Road and Bower Ave,
may take about 3 weeks.
• The closure along
Beach Road between Frosts Rd and Ascot Ave will progress
over 9 months with several sections being worked
on.
Please keep an eye out for changes and
detours.
Marine Parade, New Brighton –
night works, road closures
•
Marine Parade has CCTV investigations and
pipe lining of the wastewater main pipe between 7pm and 6am.
The work will be in 3 sections over 2 months. Section 1 is
Beach Rd to Pandora St, section 2 is Pandora to Pacific Rd,
and section 3 is Pacific Rd to Effingham
St.
Aranui/Wainoni
Please take extra care around this
busy area as SCIRT installs a new resilient vacuum
wastewater system for this community. See the Aranui map for bus routes and detours.
• Breezes Rd between Pages Rd
and Wainoni Rd will be open to two-way traffic this week, as
discussed above.
• The one-way section
of Pages Rd is shortening with the
re-opening this week to two-way traffic between Shuttle Dr
and Shortland St.
• The south side of the
Pages Rd-Rowan Ave intersection is closed
for another week.
• Merrington
Cres is one-way (towards Marlow Rd).
•
Marlow Rd remains one-way from Doreen St to
Pages Rd for road repairs.
• Eureka St
has a progressive road closure between 3 Eureka St
and Cheriton St until the end of October.
•
Portsmouth St is closed between Ben Rarere
Ave and Wainoni Rd for about 2 weeks.
•
Sandown Cres is one-way, heading south for
2 weeks.
• Carisbrooke St is
one-way between Winchfield St and the end of the cul-de-sac
for about 5 weeks.
• Corhampton St and
Netley Place have rolling road closures for 2
weeks.
The Yellow bus detour is now along Marlow Rd but please visit the Metro websitewww.metroinfo.org.nz or phone Metro Info on 366 8855 for any bus service changes.
Work in other suburbs
Redcliffs
•Moncks
Spur has one lane closed for uphill traffic between
numbers 119 and 146 for 6 months. Detour is via Glenstrae
Road. A new traffic management plan using signals is being
looked
into.
•Glenstrae
Rd has retaining wall repairs for about 5 months
from Monday 19 October. Two-way traffic will be maintained
from numbers 15 to 35 at the second uphill hairpin bend
using temporary traffic lights.
Mt
Pleasant
•Mt
Pleasant Rd (between Seamount Tce and Billys Track)
is closed. Detour via Major Hornbrook Rd or Soleares
Ave.
Parklands
•
Pegasus Ave is one-way northbound between
Philomel St and Endeavour St until December. It will have a
road closure on Wednesday 21 October between Philomel St and
Endeavour St.
• Pegasus Ave
between 22 Pegasus Ave and Royalist Ave will have a
temporary road closure for wastewater repairs for about 10
days.
• Lamorna Rd has a
progressive road closure for about 8 more weeks between
Queenspark Dr and Foresters Cres.
•
Forrest Dr has a progressive road closure
between 23 Forrest Dr and Broadhaven Ave for 6 more
weeks.
Burwood
• New
Brighton Rd between Lake Terrace Rd and Bassett St
is one lane with temporary traffic lights to maintain
two-way traffic flow. Stop/go traffic management is in place
at peak times to better manage traffic flows.
•
New Brighton Rd - Lake Terrace Rd
intersection sis closed. Access is via Burwood
Rd.
Bromley
• Wickham
Street is one way westbound from the Dyers Road
intersection to number 14, from 21 October for 3 weeks.
There is no exit from Wickham Street onto Dyers Road, with a
detour via Tanya Street, Newtown Street and Maces
Road.
Edgeware / St Albans
•
Edgeware Rd between Sherborne St and Bishop
St is one-way eastbound for about 3 months. There’s a
short detour to the local Edgeware - St Albans businesses
affected by these works. Please be a rebuild hero and make
the extra effort to support your local businesses.
•
Bishop St is one-way for
southbound traffic between Edgeware Rd and Canon St from
Monday 12 October for about 2 months. Suggested detour is
Madras St.
Merivale
•
Carlton Mill Bridge repairs are ongoing at
the Harper Ave, Park Tce and Carlton Mill Rd intersection
for about 3 more weeks. Two-way traffic remains but there
are detours for pedestrians. Please follow all
signage.
Shirley
•
Hills Rd (between Guild St and Dudley St)
is one-way northbound. Southbound traffic please slow down
along the detour, heavy traffic please take a different
route.
• Dudley St is closed
from Slater St to Hills Rd.
• Hercules
St between Marshland Rd and Sabina St will be
closed for around 3 weeks from Monday 12 October.
•
Hammersley Ave between Marshland Rd and
Sabina St will be closed for around 3 weeks from Monday 12
October.
Linwood
•
Worcester St is closed between Woodham Rd
and Dacre St, and is one-way southbound towards Linwood Ave
between Dacre St and Linwood Ave.
•
Woodham Rd is one-way city bound between
Kerrs Rd and Gloucester St. Eastbound traffic please follow
the signed detour route.
Woolston
•
Smith St has a progressive road closure
until early 2016.
• Matlock St
traffic can’t enter or exit Smith St until the end of
October.
Addington
•
Selwyn St between Harman St and Poulson St
will be one-way northbound towards Moorhouse Ave for about 4
weeks.