Centreport to Secure Cranes as Recovery Continues
TUESDAY, JANUARY 10, 2017
Centreport to Secure Cranes as Recovery Continues
Next week CentrePort will begin
work to secure its gantry cranes, as it develops plans to
resume modified container operations within four to six
months.
The 14 November earthquake caused significant
damage to the Port, especially to the container area. This
made its two gantry cranes inoperable. Each crane is 86
metres high and weighs 720 tonnes.
“Over the coming weeks we will secure the cranes, as the first stage in our plan to develop operations for customers and build resilience in case of another significant event,” Chief Executive Derek Nind said.
“Meanwhile, we continue to work with shipping lines on options for using geared ships as an interim solution. We have already had two of these visit the Port since the earthquake.
“For the medium term we are developing a plan for interim works that could restore modified container operations within four to six months. This would immediately improve CentrePort’s capacity and productivity, allowing us to serve the needs of importers and exporters in the central region. We will be keeping our customers informed as these plans develop.
“We know how important container shipping is to the regional economy. That’s why we worked hard to quickly restore limited container movements using ships with their own cranes. We are now assessing longer term options, to keep freight costs low for Wellington’s businesses.
“Over the coming days CentrePort will also
commence maintenance on the berth pockets alongside part of
Aotea Quay wharf. This will increase the flexibility of
operations at the Port, since the earthquake has damaged
Aotea Quay 1 and Thorndon Container Wharf.
“CentrePort
is grateful to its customers for their ongoing support and
patience during the recovery process.”
CentrePort’s key trades of ferries, fuel, logs, cars, and cruise ships continue to operate normally.