Heavy lifting on the Kaikoura line
Heavy lifting on the Kaikoura line
The big lift: A 102-tonne locomotive is shifted on to a trailer.
KiwiRail brought in a 132-tyre transporter to tackle the huge job of moving two locomotives that were stranded by the Kaikoura earthquake.
The first of the locomotives was lifted onto the transporter today and taken to Kaikoura. The other will make the same journey tomorrow.
“This is another sign of the good progress we are making in getting the line open again as soon as possible. More than 40 per cent of the work needed to get freight moving again is now complete,” KiwiRail Group General Manager Todd Moyle says.
“The Main North Line is an important part of our network and before the earthquake more than a million tonnes of freight was moving over the line each year.”
KiwiRail Engineering Manager Peter Dautermann says “moving the locomotives is a massive job.
“A team of specialists was needed to manage the shift. The logistics involved in preparing to move these locomotives is enormous.
“They weigh 102 tonnes each. Two cranes are needed to lift each one onto the transporter,” Mr Dautermann says.
KiwiRail freight service 737 stopped in a tunnel north of Kaikoura, near Hapuku on the morning of the 14 November earthquake last year. The freight it was carrying was taken off it in December, and the 23 wagons were lifted out and taken to Christchurch by road earlier this month.
While they waited for the shift the locomotives had been wrapped in plastic to protect them from the salt air.
Mr Moyle says the size of the task of shifting the locomotives is typical of the size of the task in re-opening the line.
“However the skill of our workforce, and the partnerships we have in the North Canterbury Transport Infrastructure Recovery alliance with NZTA means I am very confident we will get the job done.”