Planned maintenance work on HVDC link from 22 - 27 November
Thursday 22 November
Transpower is undertaking
some planned maintenance work on the HVDC link- the
transmission line running between North and South Island.
The HVDC link includes 570 km (around 530 km in the South
and 40 km in the North) of transmission line, plus 40 km of
undersea cables, and equipment at Haywards and Benmore
substation.
What are we
doing?
Every year we
undertake maintenance on our HVDC equipment (consisting of
Pole 2 and Pole 3 circuits and connected assets), to ensure
reliability is maintained throughout the year, and to avoid
unexpected outages.
This annual work is important maintenance on one of the most critical parts of our power system. We are taking the opportunity to do extra work, involving a large team of people, some of who are overseas, to service this complex equipment.
Over six days, we plan to take each circuit and connected assets out of service one at a time, with two circuits planned to be out over the weekend. This means there will be reduced capacity over the week-days and a shut down over the weekend.
We are not expecting this work to impact consumers electricity supply.
The plan has been thoroughly tested and well-thought through over a period of six months.
What happened this
morning?
Prior to the
outage Transpower as system operator was constantly
monitoring system security. The situation this morning was
assessed as tight but manageable, so the grid owner went
ahead with the outage as planned. However, due to higher
than expected demand and low wind generation available,
Transpower as system operator assessed that system security
was an issue and issued the North Island (NI) generation
warning notice. That led to Transpower as the system
operator requesting the grid owner return the HVDC to
service on short notice.
Impact to the
market
This outage has been
signalled to the market since July 2018, and Transpower, as
the system operator, will be managing the power through the
network to ensure that security is maintained. If security
of supply becomes an issue again, then Transpower, as system
operator, will once again take steps to ensure security of
supply is maintained over the shutdown.
Due to the restriction of gas in the market, prices may be higher in the North Island over the outage period.
The work is expected to be complete and the HVDC returned to full capability late on Tuesday 27th November.