Maintenance of Maungauika / North Head tunnels underway
Work is underway at Maungauika / North Head in Devonport to
maintain parts of the historic
defence tunnels.
The work includes reinforcing some of the original iron
struts within the concrete structures
and giving
additional strength to lintels above doorways. Core testing
is also scheduled to
help determine the future programme
of general upkeep.
While most tunnels will remain
open to the public, some sections of the Northern and
Southern Battery will be closed from this week. Some
small areas above ground will also
be fenced off while
this maintenance work is carried out on the structures
below. Signage is
in place.
The maintenance work will be completed by April 2020.
Nick Turoa,
Tūpuna Maunga Authority Operations Manager explains that
the work is standard
maintenance and there is no risk to
public safety if people remain outside of the cordoned
areas.
Similar works have been carried out in the past
on other heritage structures on the maunga.
“The
construction of the tunnels dates back to the late 1800’s,
and as with any heritage structure
of that age,
strengthening work may be required over time to preserve
them,” says Turoa.
“Through the process to
transition the management of Maungauika / North Head from
the
Department of Conservation to the Tūpuna Maunga
Authority mid-2019, we have been working
with engineers
to look at any remedial works required on all of the
heritage structures, including
the tunnels.”
“Engineers have identified several areas that, due to
natural corrosion, need additional
strengthening to
maintain the integrity of the tunnel structure into the
future, and that’s the
process we are working through
now.”
“We have also worked with heritage
architects to ensure that all remedial works in the tunnels
do not compromise the heritage values of the structures
and that work follows best practice for
managing
heritage assets.”
“In the meantime, the
engineers have advised us that the current day to day
visitor entry to the
tunnels is safe provided they
remain out of the cordoned areas,” says Turoa.
Coastal Track Closure
The
coast track that runs around the base of Maungauika / North
Head has been closed since
August 2019 due to a large
landslide that took place during a storm event. Over the
past months
the Tūpuna Maunga Authority have been
working with geologists and geotechnical engineers
to
ensure the structural stability of the cliff face.
Assessment works have now been complete. Engineers have
recommended scaling the cliff
face of loose materials
and removing dead vegetation to minimise risk of further
landslide or
loose rocks falling on track users.
Works on the cliff face will begin early 2020 and the
coastal track will be re-opened once
engineers deem it
is safe for public access.
Visit www.maunga.nz for more information about the Tūpuna Maunga Authority.