Wastewater Plant Upgrade Project Enters Final Phase
The Pukete Wastewater Treatment Plant is speeding through its current upgrade, a $56 million project, which will see Hamilton Kirikiriroa with one of the largest wastewater inlet screening facilities in the country.
Wastewater is the liquid that is flushed
from our bathrooms, kitchens, and laundries, and usually
includes additional chemicals and solids. As the first step
in the treatment process, these inlet screens filter out
solid objects that make their way into the system before the
wastewater is treated.
The secondary treatment
process at the plant has also had an upgrade, with a new
basin (bioreactor), clarifier, and pump station that
increases both the performance of the plant and the amount
of wastewater able to be processed each day.
The
next phase of the current upgrade project includes updating
some of the existing plant to match the performance of the
new infrastructure.
Hamilton City Council’s City
Waters Unit Manager, Maire Porter, said these upgrades will
ensure our wastewater continues to comply with Waikato
Regional Council
standards.
“Investing in this upgrade is a part of Council’s renewal and upgrade programmes, which aim to ensure our city’s assets can cater for Hamiltonian’s wastewater needs now, and in the future, as our city grows,” she said.
The skills and commitment of the plant’s project and operations teams have been an important factor in the success of the treatment plant. However, Council wants to encourage the wider community to play their part by watching what they flush.
“The team have worked incredibly hard to
manage recent large flows of wastewater at the plant,”
said Porter.
“It’s really important that we work together as a community to decrease the amount of unwanted materials and chemicals being flushed into the system, which can affect the performance of the plant and the safety of our people.”
The biggest
culprit is wet wipes, but the team have found everything
from children’s toys to blocks of timber caught in the
inlet screens.
Work on the Pukete Wastewater
Treatment Plant Stage 3 Upgrade project began in 2018 and is
expected to be completed in 2024.
The first two
phases included the installation of the new bioreactor
basin, clarifier and a second onsite pump station, as well
as improvements to the plant’s chemical storage
facility.
The final phase involves the
retrofitting of the four existing bioreactors, testing the
new technology and upgrading the inlet screening
facility.
Find more information on the Pukete Wastewater Treatment Plant |