Taipa Subsidence Work Extended

Due to challenging ground conditions, subsidence work on State Highway 10 near Bush Point Road in Taipa needs to be extended, and will not be completed before Easter.

Geotechnical testing for NZ Transport Agency Waka Kotahi (NZTA) has revealed poorer than expected underlying ground conditions, necessitating additional mitigation before the road can be rebuilt.

Contractors have already installed improved drainage systems and started building up pavement layers to enhance the road's lifespan.

The team is working hard to minimise the impact over the school holidays, but road users should expect delays of up to 8 minutes here as stop/go traffic management and a 30km/h temporary speed limit remain in place until Sunday 4 May. The traffic management will remain in place over the Easter holidays and Anzac weekends, where increased traffic volumes mean road users may experience longer delays.

These works are weather dependent.

This work is part of the Northland Subsidence Programme, which targets uneven road surfaces caused by land movement. Rebuilding the road often involves replacing all or most of the structural layers, helping improve the safety, resilience, and long-term performance of the highway network.

NZTA thanks road users for their patience while we work to improve the resilience and condition of this important route.

Plan for a safe, enjoyable journey. Keep up to date with:

  • Traffic updates
  • Facebook
  • X
  • Journey Planner
  • Phone: 0800 4 HIGHWAYS (0800 44 44 49)
Advertisement - scroll to continue reading

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels