Mitigation Agreements – Designed To Be Flexible
Media release
For immediate distribution: Wednesday
19 November 2003
Mitigation Agreements – Designed To Be Flexible
Meridian Energy is reassuring residents and businesses potentially affected by Project Aqua that the formal Mitigation Agreements could still be changed by agreement even after being signed by the parties.
Project Aqua is a proposed hydro-electric scheme that would run along the south side of the lower Waitaki Valley. It would generate enough low-cost, renewable electricity to power the equivalent of about 375,000 households in an average year and about 250,000 households in a very dry year. A very dry year is a 1-in-20 year event.
Meridian Energy is currently providing Directly Affected Parties with formal Mitigation Agreements for consideration. These agreements set out the understanding between Meridian Energy and Directly Affected Parties about how the effects of Project Aqua will be addressed. Meridian Energy is committed to ensuring fair and reasonable agreements are negotiated to mitigate the anticipated adverse effects of Project Aqua. Mitigation Agreements also provide certainty over what mitigation measures would be provided should Project Aqua proceed.
Some people and groups have asked for clarification about the ability to change the formal agreements if new information comes to light throughout the process.
“ If there is new and relevant information, Meridian Energy will review the Mitigation Agreements and if necessary, make any appropriate changes,” says Meridian Energy spokesperson Alan Seay.
“Some Directly Affected Parties may choose not to sign until they feel they have all the information they require. For those that chose to sign, the agreement provides that if the effects are different than those anticipated at the time of signing the agreement, then Meridian Energy must renegotiate the mitigation package in good faith.”
“Once someone signs the formal Mitigation Agreement, then a legally binding agreement is in place but it still depends on all the consents and approvals being obtained for Project Aqua to proceed and Meridian Energy being satisfied that the scheme is technically and commercially viable,” says Mr Seay.
“Mitigation is a major focus for Meridian Energy and we want to get it right and provide certainty for Directly Affected Parties,” concluded Alan Seay.
Background
What is
mitigation?
- The Resource Management Act requires a
resource consent applicant (in this case, Meridian Energy)
to avoid, remedy or mitigate as far as practicable any
adverse effects resulting from its activities.
-
Mitigation means to lessen or reduce any identifiable
adverse effects.
- The proposed activities in this case
are the construction and the operation of Project
Aqua.
What are the possible effects?
- Most of the
time for most of the Directly Affected Parties, the effects
are expected to relate to one or the other of a combination
of dust, noise, visual or vibration.
- If the project
proceeds, there will also be community wide effects, which
are still being assessed.
What is a Mitigation Agreement?
- Mitigation agreements set out the understanding
between Meridian Energy and Directly Affected Parties about
how the effects of Project Aqua will be addressed.
-
Meridian Energy is committed to ensuring that thorough and
reasonable mitigation agreements are negotiated with
Directly Affected Parties to mitigate the anticipated
adverse effects of Project Aqua. Mitigation agreements will
provide certainty for Directly Affected Parties over what
mitigation measures would be provided should Project Aqua
proceed.
- The agreements will be subject to Meridian
Energy obtaining all necessary approvals and authorisations
to allow Project Aqua to proceed, and being satisfied that
Project Aqua is technically and commercially viable.
-
If Project Aqua does not go ahead for some reason, there
will be no need to provide the mitigation.
- Mitigation
agreements and payments to Directly Affected Parties are
lawful and a commonly accepted practice.
What is Meridian
Energy offering?
- There are aspects of the mitigation
agreements that are similar for all Directly Affected
Parties and aspects that differ depending on how individuals
are impacted.
- Meridian Energy has spent considerable
time and effort exploring all the mitigation options so that
the most appropriate package can be developed for each
Directly Affected Party.
- Meridian Energy is offering
financial support to people to obtain professional advice
and in recognition of the time and effort taken in
negotiating, considering and agreeing to the mitigation
agreement.
- Meridian Energy is also offering solatium
payments, which are in summary, a form of financial
recognition for the temporary inconvenience, loss of
enjoyment, and the short–term impact on the marketability of
identified property assets during the period of time that
they will be directly affected by construction.
- These
mitigation measures demonstrate the importance of mitigation
to Meridian Energy.
What are some of the mitigation
measures, apart from financial mitigation, that Meridian
Energy is offering?
- Mitigation could include some or
all of the following:
- Double glazing and air
conditioning
- Constructing or upgrading existing
boundary fences
- Clothes dryers
- Temporary
relocation or property purchase
- Business loss that is
not offset by Project Aqua
- Monitoring for vibration
effects and remedying faults caused by construction
Internal and external property cleaning.
ENDS