Preliminary Results of the Didipio Optimisation Study
OceanaGold Announces Preliminary Results of the
Didipio Optimisation Study
MEDIA
RELEASE
12 September 2014
(All figures in
US Dollars unless otherwise stated)
(MELBOURNE)
OceanaGold Corporation (TSX/ASX/NZX: OGC)
(the “Company”) announced today the preliminary results
of the Didipio Optimisation Study (the “Study”), a
project that has identified significant value from the
existing operation and ore body. The Study is expected to be
finalised early in the fourth quarter with completion of an
updated National Instrument (“NI”)43-101 Technical
Report.
Key Outcomes
• Underground
development to be brought forward by one year to commence in
the first quarter 2015.
• Access to high grade ore to be brought forward by two years with first underground production now expected to be in the third quarter of 2017 with full ramp-up to a mining rate of 1.6 million tonnes per annum (“Mtpa”) by 2020.
• Redesigned underground to include two underground mining domains that will increase the mine productivity rate to 1.6 Mtpa (from 1.2 Mtpa) over a longer underground mine life.
• Improved geotechnical understanding, optimized open pit design and revised open pit/underground interface will reduce open pit waste mining by nearly 70 million tonnes (Figure 3) whilst only reducing ore supplied from the open pit by approximately one year.
• Improved project economics including increased
cash flows and a longer mine life – to be finalized in the
updated NI 43-101 Technical Report.
Mick Wilkes, Managing
Director and CEO said, “On behalf of the Board of
Directors, I am pleased to announce the positive outcomes
from the Didipio Optimisation Study. With nearly 18 months
of commercial operations, we have identified significant
value from the Didipio Mine that will be unlocked through
increased metal production; improved operating cash flows;
as well as a significant reduction in waste mined combined
with earlier access to higher grade underground
ore.”
Based on the results of the Study, the
underground portion of the Didipio operation will be brought
forward by one year with development expected to commence in
the first quarter of 2015 subject to receiving final
regulatory approvals. Access to high grade ore will be
brought forward by two years with first ore delivered for
processing in the third quarter of 2017. The underground
crown pillar will now be established at RL2460 (Figure 1),
approximately 80 metres higher than in the original plan
thus allowing for two active production areas in the
underground resulting in an increase of the mining
productivity rate to 1.6 Mtpa and a reduction in the cut-off
grade. Additionally, the detailed Study along with a
comprehensive infill drill program during the last 12 months
has resulted in the expansion of the underground by 170
meters deeper than originally planned to RL2010 (Figure
1).
"Commencing the underground operation earlier
than originally planned enables faster access to the high
grade ore that resides in the underground reserves of the
ore body. It also allows us to carry out further exploration
at depth where we believe high grade mineralisation
continues below the extent of the current drilling,” Mr.
Wilkes said.
As a result of the Company’s increased
understanding and confidence in the geotechnical attributes
of the mine, the open pit has been redesigned with a reduced
Stage 6 pit shell resulting in the elimination of nearly 70
million tonnes of waste over the life of mine.
The Board
of Directors has endorsed the Study including the earlier
commencement of the underground mine development, resource
definition drilling and redesigned open pit. The Company
will seek the required approvals to commence the development
of surface facilities, including the portal and ventilation
infrastructure in the first quarter of 2015. Under the
optimised underground design, the pre-production capital
cost is now estimated to be approximately $110 million over
a three-year period (2015-2017) and sustaining capital
expenditure over the life of the underground mine is
expected to average $7 to $8 million per annum.
Mr.
Wilkes added, “Over the coming months, the Company will
invest in additional resource definition drilling for
resource conversion and to further prove out the ore body.
The Company will release an updated NI 43-101 Technical
Report that will include the final results and an update to
the Reserves and Resources statement for Didipio.”
-
ENDS
-