KiwiRail responds to TAIC report on Aratere

Media Release

15 December 2017

KiwiRail responds to Aratere report

The Transport Accident Investigation Committee’s report into the loss of the Interislander ferry Aratere’s propeller in 2013 makes valuable recommendations around the standard for advanced propeller manufacture, KiwiRail Group General Manager Todd Moyle says.

“Having tighter manufacturing tolerances for large fixed pitch propellers - like those used on the Aratere - is an important step in ferry safety and is a key recommendation in the report.

“We agree with TAIC’s finding that the fracture which caused the propeller to come off was the result of bending forces. Our own extensive investigation, led by the international engineering consultancy firm Aurecon, concluded the likely cause of those forces was an irregularity in the propeller blade due to the manufacturing process used.

“However we do not accept TAIC’s view that KiwiRail did not follow the manufacturer’s advice on the best way to fit the propellers and that if we had, some of the conditions that contributed to the shaft’s failure would have been less likely to have happened.

“The proposed method of fitting the propellers was impractical because of the very long shaft fitted. The method we did use to fit the propellers was discussed with the manufacturer, who accepted it as an alternative.

“KiwiRail has accepted TAIC’s recommendation on document management practices and record keeping around the fitting process.

Advertisement - scroll to continue reading

“As TAIC notes, KiwiRail has already implemented the recommended change by ensuring significant modifications follow Project Management Office procedures, which include strong governance and good record keeping practices.

“I should also emphasise that during this incident the ship was always under control and at no point were passengers or the vessel at any risk. This was not a safety issue.

“The Aratere is the hardest working of the Interislander ferries. Already this year it has completed more than 1200 Strait crossings, carried more than 15,000 trucks and 54,000 cars, along with 180,000 passengers and more than one million gross tonnes of rail freight, despite being in Singapore for more than two months for its regular survey.

“It had 95% reliability in the last financial year. The Aratere is a real workhorse for New Zealand,” Mr Moyle says.

All Interislander ferries and facilities are fully operational for the peak Christmas season after the disruption caused by the Kaikoura earthquake.


© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Business Headlines | Sci-Tech Headlines

 
 
 
 
 
 
 
 
 
 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.