Nelson And Marlborough’s Best In Civil Construction Revealed
A cycle track built in extreme conditions, a land reclamation project with exceptional environmental controls, and a talented young operations manager were among the outstanding civil construction projects celebrated at the Civil Contractors NZ Nelson Marlborough Awards Dinner on Friday.
Around 300 guests attended the ceremony at the Rutherford Nelson Hotel on 6 August, coming together to applaud the people and companies doing challenging and vital work at the top of the South Island.
Fulton Hogan was the big winner on the night, with their Champion/Salisbury Road Roundabout Upgrade sweeping the Hynds Projects Over $1.5 Million prize and the coveted Hirepool Supreme Award. The company’s Renwick and Havelock Watermeter Contract also bagged the Judges Recognition Award.
The Champion/Salisbury Road Roundabout Upgrade was completed on behalf of Tasman District Council on a high traffic flow road, which sees in excess of 18,000 vehicles per day. More than 13,500 hours went into the project, which won for its innovative solutions, strong communication, and inclusive community liaison.
The Renwick and Havelock Watermeter Contract was established to reduce water waste on behalf of Marlborough District Council, as their area historically used three times as much water per person compared to Nelson. Fulton Hogan installed 1,300 new water meters as part of the project, which won plaudits for stakeholder engagement and data control.
Mike Edridge Contracting Ltd also did well, securing two wins - one for the Southwater Projects Valued $0 - $50,000 for the design and build of the Bannochburn Fire Pond, a 400m3 self-filling pond to help fight fires. The other was for Total Oil NZ Projects Valued $50,001 - $200,000 for the Wither Hills Reservoir Slope Re-Profiling, a 1,300-hour project to improve access to the slope for walkers and cyclists, as well as to make it more stable during earthquakes.
Nelmac took the prize for Cable Price Projects Valued $200,001 - $ 750,000 for its work on the Poormans Stream Shared Pathway. This 2.5-metre-wide pathway passes along a stream and through numerous nature reserves in Nelson. Nelmac received the award for maintaining constant communication and cooperation with the public and ecologists throughout the project.
Taylors Contracting Co won the award for Land Dimensions Ltd Projects Valued $750,001 - $1.5 Million for Seafield Terrace Rock Revetment. This project saw the company supply and place 5,000 tonnes of rock armouring for a sea wall in a marine reserve area, which included new outlets, footpaths and pavements. The company was recognised for its tight communication between residents and the Department of Conservation.
Simcox Construction took the Tasman District Council Environmental Award for the Separable Portion 1 – Waikawa Marina project, which involved reclaiming 460 metres of land along The Snout with 4,000 tonnes of rock. The company filled 33,000m3, built timber boardwalks, and dredged the Waikawa stream, with their work exceeding expectations for environmental control.
The Health and Safety Professionals Innovation Award was won by Nelmac for its work on the Pike29 Memorial Track – a 10.7km cycle and walking trail linking to the Paparoa Track. It took 29,000 hours, including 70 helicopter hours, with teams living and working on site in extremely harsh weather conditions and on difficult terrain. Nelmac was given the award for their innovative techniques to get such a challenging project completed, prioritising the safety of workers above everything else.
The Nelson City Council Health and Safety Award was presented to Downer NZ. This was for its overall health and safety record across all the projects it submitted for judging.
There was also a CCNZ Nelson Marlborough Branch Supplier of the year award, presented to Hynds Pipe Systems by popular vote from industry peers on the night.
And lastly, the Bank of New Zealand Young Achiever Award went to Nick Webby of Fulton Hogan. The 30-year-old is Operations Manager for the Tasman Journeys NOC Contract and has been with Fulton Hogan since 2007. He impressed the judges because of his adaptability to change, travelling offshore and learning another language to help achieve desired contract results.
Award judges Bruce Taylor and Peter Fisher said the standard of entries was extremely high this year.
“Judging these awards has been an amazing reminder of the great work taking place in this part of New Zealand,” Mr Fisher said. “From the way we get around, to the water we drink, and the activities we take part in, none of it could be possible without these outstanding companies and the people they employ.”
CCNZ Nelson Marlborough’s Chairman Brendan Dodd agreed, saying Friday’s awards ceremony was a highlight of the annual calendar for local contractors.
“I am sure we all left feeling truly inspired by all of the hard work and dedication that goes on in Nelson Marlborough’s civil construction industry, day after day.”
Amongst the attendees were four Life Members - Snow Edgar, Charlie Taylor, Mike Edridge, and judge Bruce Taylor.
Ahead of the prize giving, a minute’s silence was held in memory of Denis Chambers, a CCNZ Nelson Marlborough Life Member who recently passed away.
Winners: CCNZ Hirepool Construction Excellence Awards 2021
Southwater Projects Valued $0 - $ 50,000
Winner: Mike Edridge Contracting
Ltd – Bannochburn Fire Pond
Client: One Forty
One Ltd
Value: $45,700
Mike Edridge Contracting designed and built a 400m3 HDPE Lineal Pond for firefighting purposes in Bannochburn Forest in the Awatere Valley. The pond is self-filling, utilising surrounding water run-off. It was designed using a GPS model pond, and was completed on budget and on time, in a total of 250 hours.
Total Oil Projects Valued $50,001 - $ 200,000
Winner: Mike
Edridge Contracting Ltd – Wither Hills Reservoir Slope
Re-Profiling
Client: Marlborough District
Council
Value: $152,000
This project involved the re-profiling of a slope behind the Marlborough District Council water supply reservoir. Mike Edridge Contracting had to contend with tough Chilean needle grass during the project, which they managed ably. The company improved slope stability for during earthquakes, as well as public access for walkers and cyclists. It took 1,300 hours to complete.
Cable Price Projects Valued $200,001 - $ 750,000
Winner: Nelmac – Poormans
Stream Shared Pathway
Client: Nelson City
Council
Value: $600,000
This project involved development of 2.5-metre-wide pathway along the true left bank of a stream from Main Rd Stoke to Neale Ave, taking in Greenmeadows Reserve, Isel Park and Neale Ave Reserve. The project used Magnum Stone Product as retaining wall, and involved reshaping of the stream edge, removal of redundant services, fish salvaging, an ongoing partnership with project ecologists, and emphasis on sediment control, bunding, fencing and site security. Communication with the public was of the utmost importance and Nelmac did this in outstanding fashion.
Land Dimensions Ltd Projects Valued $750,001 - $1.5 Million
Winner:
Taylors Contracting Co – Seafield Terrace Rock Revetment
Works
Client: Nelson City Council
Value: $1
Million +
Taylors Contracting celebrated its
50-year anniversary recently, demonstrating its resilience
and ability to withstand changing market conditions and the
many project challenges that have come its way. The
company’s work on the Seafield Terrace Rock Revetment
Works saw it commit more than 4,600 hours into supplying and
placing 5,000 tonnes of rock armouring for a sea wall in a
marine reserve area. The project area was 250 metres long,
7.5-8 metres wide at base, three metres wide at top, and
completed in 15-21 metre sections. The team built a new
culvert outlet, sumps, footpath and pavement. Communication
during the project was tight between residents, iwi and the
Department of Conservation.
Hynds Award for
Projects Over $1.5 Million
Winner:
Fulton Hogan - Champion/Salisbury Road Roundabout
Upgrade
Client: Tasman District
Council
Value: $2.015 Million
This was a high traffic flow project on a road that receives more than 18,000 vehicles a day. It was completed eight weeks early, in a total of 13,544 hours. The team used innovative solutions to overcome safety challenges. There was inclusive community liaison and traffic management was of the utmost importance. Communication skills and thinking outside of the box were Fulton Hogan’s strengths during this project.
Hirepool Supreme
Award
Winner: Fulton Hogan -
Champion/Salisbury Road Roundabout
Upgrade
(See above)
Tasman
District Council Environmental
Award
Winner: Simcox Construction –
Separable Portion 1 – Waikawa Marina
Client:
Port Marlborough NZ
Value: $3.150 Million
Four
hundred and sixty metres of land along The Snout in Pictor
was reclaimed, using 4,000 tonnes of rock to fill in
33,000m3 area. The project saw 3,000 trucks and trailers
passing through the heart of Picton, took 3,500 hours to
complete, and involved the dredging of Waikawa Stream. Five
large diameter concrete culverts and manholes were
installed, along with timber boardwalks and jetty abutments.
The overall environmental control on the project exceeded
expectations in all areas.
Health and Safety
Professionals Innovation Award
Winner:
Nelmac – Pike29 Memorial Track
Client:
Department of Conservation
Value: $2.54
Million
A 10.7 km cycling track was built along
the Pike29 Memorial Section of the Paparoa Track. It took
29,000 hours to complete, including 70 helicopter hours. Two
crews of three people worked seven days on/seven days off,
living and working on site, where accommodation and cooking
facilities were provided. The teams worked through difficult
terrain in all weathers, including snow, wind and mud. It
was a challenging job in extreme conditions, which saw them
remove 850m of rock using explosives, as well as felling
trees, installing culverts, and laying forming pads for the
diggers. Safety was considered first and foremost, taking
priority over productivity.
Nelson City Council
Health and Safety Award
Winner: Downer
NZ
Given for exceptional overall health and safety on all their submitted projects.
Judges
Recognition Award
Winner: Fulton Hogan
– Renwick & Havelock Watermeter
Contract
Client: Marlborough District
Council
Value: $1.4 Million
The team installed
new water meter manifolds to Renwick and Havelock
communities, with over 1,300 individual property
installations completed over 11,379 hours. This was done to
reduce water waste caused by leakages in both private and
public land caused be an ageing line. Historically, around
900 litres of water were used per person, which was very
high compared to Nelson’s 250 litres per person. The
project’s success was down to high levels of public
communication, good stakeholder engagement, accurate data
control, and well-kept documents.
CCNZ Nelson
Marlborough Branch Supplier of the Year
Award
Winner: Hynds Pipe
Systems
As voted by industry peers on awards night.
Bank of New Zealand Young Achiever
Award
Winner: Nick
Webby
Employer: Fulton Hogan
Age: 30 years
old
Nick is Operations Manager of the Tasman
Journeys NOC Contract. He started with Fulton Hogan in 2007,
and has experience as a Sealing Manager, Paving Manager, and
having worked on the 2013 Wellington Hybrid and NOC
Contracts. Nick received this award because of his
adaptability to challenge and see projects through to
conclusion, being prepared to travel offshore and learn
another language in order to achieve the desired contract
results. He constantly gets supportive and favourable
comments from senior management
teams.