Transpower has published its six monthly monitoring report on the transformation of Aotearoa New Zealand’s energy system towards assisting the net zero carbon transition. It shows that while good progress is being made, this must be built upon.
“It’s great to see some traction towards decarbonising the energy system,” says Transpower’s General Manager Strategy and Customer, Richard Hobbs.
“We are clearly now in the early stages of a concerted push towards a much more renewable electricity system driven by low cost wind and solar. The quadrupling of electric vehicle (EV) registrations in recent months has been headline grabbing but has come from a very low base. Good progress is also being made on process heat decarbonisation, both through electrification and biomass conversions,” says Richard Hobbs.
“However, despite progress towards a net zero carbon future, events in the past six months remind us that decarbonisation, the sustainability leg of the energy trilemma, cannot happen without consideration of the other two legs: affordability and reliability where we have clearly had issues.”
The report is part of its Te Mauri Hiko programme of work, which includes an Electrification Roadmap for the transport and process heat sectors. It gives a snapshot of progress and scenarios on how decarbonisation might progress over time. Its publication is timely given the recent release of the government’s emissions reduction plan (ERP) discussion document.
Highlights from the report include:
Moving towards a much more renewable
electricity system
Transpower continues to
see record enquiries for new connections of renewable
electricity projects, mostly wind and solar. Overt he last
six months, around 683MW of new wind and geothermal has
either been fully commissioned, commenced commissioning or
commenced construction. 1
Tiwai’s future remains uncertain, but that, coupled with much discussion of potential new demand from data centre or hydrogen facilities, means the demand for generation additions remains robust. There is also more interest, and recent announcements, in storage technologies like batteries.
More follows…
Transport
electrification
Transport electrification
received a major boost with the start of the Clean Car
Discount policy with record registrations in July and
September. These were four times the historic average. While
this is a good start, what will be important is that this
high rate of new electric registrations is sustained over
the long term. The Clean Car Standard, which will set fleet
average import standards for importers, should have a
significant role to play in reducing the long-term
emissions.
Decarbonising process
heat
Recent announcements, many backed by the
Government Investment in Decarbonising Industry (GIDI) fund,
show progress is being made towards the decarbonisation of
process heat. The fund is delivering emissions reductions at
a remarkably cost effective ~$9 per tonne of CO2 reduced.
Biomass and electrification have been the main technologies.
It is hoped that those projects already underway will help
build momentum and sector capacity for further
decarbonisation.
“Overall, the outlook is a reasonable one. Some good progress is being made, but it’s essential this is not just maintained, but built upon if Aotearoa is to truly live up to its aspirations for a much more renewable energy system by 2030 and a net-zero carbon economy by 2050. It is also essential that the performance of the affordability and reliability aspects of the energy trilemma are kept at the fore of the transition to support decarbonisation. There are ample cost-effective technologies and policy options to do so and it is good to see some momentum building,” says Richard Hobbs.
For more information call Transpower Communications on 021 195 8613
- Electricity development over the past six months.
Development | Size | Type | Status |
Waipipi (Tilt) | 133 MW | Wind | commissioned |
Turitea (Mercury) | 222 MW | Wind | commenced commissioning |
Tauhara (Contact) | 152 MW | Geothermal | commenced construction |
Harapaki (Meridian) | 176 MW | Wind | commenced construction |