Busway Traffic Bulletin, August 12-18
Busway Traffic Bulletin, August 12-18
Transit New Zealand advises motorists of proposed closures for work on State Highway 1 for the construction of the Northern Busway over the next week (weather permitting).
Should unforeseen circumstances present work on the dates below, the work will be postponed until the next fine night.
Sun 13 and Mon 14
August
SOUTHBOUND MOTORWAY CLOSURE
All SH1 southbound
motorway lanes between Constellation Dr and Tristram Ave –
CLOSED – overnight from 10.30pm until 5am for barrier
placement:
• All southbound traffic will be diverted
off the motorway at Constellation Drive and follow the
sign-posted detours via East Coast Rd, along Forrest Hill Rd
and then on to Tristram Ave before re-entering the motorway
at the Tristram Ave southbound on-ramp.
• Motorists
to use Northcote Rd on-ramp as alternatives.
• As part
of this closure the Constellation Drive SH1 southbound
on-ramp will also be closed at the same times.
Mon 14 and
Tues 15 August
NORTHCOTE RD
The southbound off-ramp
from SH1 to Northcote Rd – CLOSED – overnight from 9pm
until 5am for installation of temporary works:
•
Motorists to use Tristram Ave or Onewa Rd off-ramps as
alternatives.
• As part of this closure Northcote Rd
eastbound between Taharoto Rd and the southbound motorway
ramps will be closed at the same time.
Wed 16 and Thurs 17
August
ESMONDE RD
The northbound off-ramp from SH1 to
Esmonde Rd – CLOSED – overnight from 9pm until 5am for
installation of drainage:
• Motorists to use Onewa Rd
or Northcote Rd off-ramps as alternatives.
• As part
of this closure the Akoranga Dr eastbound link to Esmonde Rd
will be closed at the same times.
Wed 16 and Thurs 17 August
TRISTRAM AVE
The southbound on-ramp from
Tristram Ave to SH1 – CLOSED – overnight from 9pm until
5am for the realignment of the on-ramp:
• Motorists to
use Constellation Dr or Northcote Rd on-ramp as
alternatives.
Transit New Zealand apologises for any inconvenience caused.
Transit New Zealand Northern Busway Project Director Clive Fuhr (09) 486 0054
Visit www.busway.co.nz or www.transit.govt.nz for more information on the project.
Ends