Scoop has an Ethical Paywall
Licence needed for work use Learn More

Gordon Campbell | Parliament TV | Parliament Today | News Video | Crime | Employers | Housing | Immigration | Legal | Local Govt. | Maori | Welfare | Unions | Youth | Search

 

CRL: Greater Transparency Needed For Our Largest Infrastructure Project

A seven-page report accidentally made public has revealed major concerns for cost blowouts and time delays for New Zealand’s largest infrastructure project, the City Rail Link.

“Human error has given us a glimpse into how dire the situation really is” said Auckland Ratepayers’ Alliance Spokesman, Sam Warren.

“Critically, the material shows a lack of confidence in the project’s main contractor, French company, VINCI Grand Projects."

“If this was entirely a government project, greater tools for transparency would be available. However due to the structure of the joint company set up between Auckland Council and the Government that oversees the CRL, scrutiny is near impossible."

"The initial $2b–$3b budget has exploded to $5.5b since the project started in 2016. It shouldn't take human error to keep the public informed. If this massive undertaking is in danger of blowing out further, it’s well within the public’s interest to know."

"We’re calling for greater transparency from City Rail Link Limited to release any and all critical information surrounding setbacks, delays and cost overruns, so that officials and contractors involved can be held accountable.”

Advertisement - scroll to continue reading

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.